Activity ID,WBS,Activity name,Type,Trade,Start,Finish,Duration (wd),Predecessor,Crew,Weather sensitivity,EV method,Location ACT-001,1.1,Mobilization and site logistics,Summary,Sitework,2026-03-02,2026-04-11,29,,10,Rain / wet,milestone,Whole building ACT-002,1.2,Mass excavation and shoring,Summary,Sitework,2026-04-11,2026-06-22,52,ACT-001,12,Rain / wet,units,Whole building ACT-003,1.3,Foundations and below-grade,Summary,Concrete,2026-06-22,2026-10-03,74,ACT-002,14,Freeze / cold,percent,Whole building ACT-004,1.4,Superstructure,Summary,Structure,2026-10-03,2027-04-26,147,ACT-003,16,Wind,units,Whole building ACT-004-01,1.4.1,"Level 1 — frame, deck and pour",Task,Structure,2026-10-03,2026-10-19,12,ACT-004,14,Wind,units,Level 1 ACT-004-02,1.4.2,"Level 2 — frame, deck and pour",Task,Structure,2026-10-19,2026-11-04,12,ACT-004-01,14,Wind,units,Level 2 ACT-004-03,1.4.3,"Level 3 — frame, deck and pour",Task,Structure,2026-11-04,2026-11-20,12,ACT-004-02,14,Wind,units,Level 3 ACT-004-04,1.4.4,"Level 4 — frame, deck and pour",Task,Structure,2026-11-20,2026-12-06,12,ACT-004-03,14,Wind,units,Level 4 ACT-004-05,1.4.5,"Level 5 — frame, deck and pour",Task,Structure,2026-12-06,2026-12-22,12,ACT-004-04,14,Wind,units,Level 5 ACT-004-06,1.4.6,"Level 6 — frame, deck and pour",Task,Structure,2026-12-22,2027-01-07,12,ACT-004-05,14,Wind,units,Level 6 ACT-004-07,1.4.7,"Level 7 — frame, deck and pour",Task,Structure,2027-01-07,2027-01-23,12,ACT-004-06,14,Wind,units,Level 7 ACT-004-08,1.4.8,"Level 8 — frame, deck and pour",Task,Structure,2027-01-23,2027-02-08,12,ACT-004-07,14,Wind,units,Level 8 ACT-004-09,1.4.9,"Level 9 — frame, deck and pour",Task,Structure,2027-02-08,2027-02-24,12,ACT-004-08,14,Wind,units,Level 9 ACT-004-10,1.4.10,"Level 10 — frame, deck and pour",Task,Structure,2027-02-24,2027-03-12,12,ACT-004-09,14,Wind,units,Level 10 ACT-004-11,1.4.11,"Level 11 — frame, deck and pour",Task,Structure,2027-03-12,2027-03-28,12,ACT-004-10,14,Wind,units,Level 11 ACT-004-12,1.4.12,"Level 12 — frame, deck and pour",Task,Structure,2027-03-28,2027-04-13,12,ACT-004-11,14,Wind,units,Level 12 ACT-005,1.5,Building envelope,Summary,Envelope,2027-04-26,2027-09-28,111,ACT-004,18,Wind,percent,Whole building ACT-006,1.6,MEP rough-in,Summary,MEP,2027-09-28,2028-03-11,118,ACT-005,20,None,percent,Whole building ACT-007,1.7,Interior build-out,Summary,Interiors,2028-03-11,2028-07-23,96,ACT-006,22,None,percent,Whole building ACT-008,1.8,Finishes and fit-out,Summary,Finishes,2028-07-23,2028-10-13,59,ACT-007,24,None,percent,Whole building ACT-009,1.9,Commissioning and turnover,Summary,Commissioning,2028-10-13,2028-12-24,52,ACT-008,26,None,0-100,Whole building ACT-900,1.10,Substantial completion,Milestone,Commissioning,2028-12-24,2028-12-24,0,ACT-009,0,None,milestone,Whole building