Ref,Package,Trade,CSI,Estimated cost,Lead time (weeks),RFQ due,Required on site,Status BP-001,Structural steel — mill order and fabrication,Structural,05 12 00,2944100.00,34,2026-04-01,2026-11-25,Awarded BP-002,Curtain wall / envelope package,Envelope,08 44 13,1668300.00,30,2026-05-01,2026-11-27,Awarded BP-003,Electrical switchgear and distribution,Electrical,26 24 13,1079500.00,46,2026-05-31,2027-04-18,Draft BP-004,Air handling units,Mechanical,23 73 00,883200.00,32,2026-06-30,2027-02-09,Draft BP-005,Elevators,Conveying,14 21 00,549600.00,40,2026-07-30,2027-05-06,Draft BP-006,Roofing membrane and insulation,Envelope,07 54 00,431800.00,16,2026-08-29,2026-12-19,Draft BP-007,Guestroom FF&E package,Furnishings,12 50 00,1177600.00,28,2026-09-28,2027-04-12,Draft