WORKDAY Function
The WORKDAY function is one of the date and time functions. It is used to return the date which comes the indicated number of days (day-offset) before or after the specified start date excluding weekends and dates considered as holidays.
Syntax
WORKDAY(start_date, days, [holidays])
The WORKDAY function has the following arguments:
| Argument | Description |
|---|---|
| start_date | The first date of the period entered using the DATE function or other date and time function. |
| days | A number of nonweekend before or after start_date. If the days has the negative sign, the function will return the date which comes before the specified start_date. If the days has the positive sign, the function will return the date which follows after the specified start_date. |
| holidays | An optional argument that specifies which dates besides weekends are nonworking. You can enter them using the DATE function or other date and time function or specify a reference to a range of cells containing dates. |
Notes
How to apply the WORKDAY function.
Examples
The figure below displays the result returned by the WORKDAY function.