--- name: epic-tickets description: Principles for writing, updating and reviewing tickets that hold a body of work, in any issue tracker, for any team, whatever the tracker calls them, such as an epic, project, initiative, milestone, parent issue or tracking issue. Use this whenever you create one, plan a piece of work too large for a single ticket, or are asked to break a feature, project or goal down into tickets. Use it when stating the goal, saying what done means for the whole, listing what is deliberately left out, and deciding what belongs in the epic and what belongs in a design document. Use it when deciding how to slice the work, what to build first, how far ahead to write the child tickets, and whether a group of tickets is one epic, several, or only a category. Use it after filing too, when you write a status update, record a decision, cut or add scope, or close the epic, and when deciding whether a note belongs on the epic, on a child ticket or with the code. Also use it when reviewing someone else's epic or breakdown, or briefing someone to write one. It is about how to think, not about any one tracker's hierarchy or any one planning method. --- # Epic tickets An epic holds a body of work that is too large for one ticket and still has an end. Linear's team puts the whole idea in two short sentences, and everything below follows from them: > Issues want to be done. Projects want to be done. ## What an epic is - **One goal, reached through several tickets.** Mike Cohn's definition is simply a story too big to finish in one go. - **It has an end.** There is a state of the product in which the epic is finished, and it can be described before the work starts. - **It is the top of a small tree.** Its children are stories, tasks and bugs, each written to its own skill. The epic says what they add up to. - **Its name depends on the tracker.** Epic, project, milestone, parent issue. Cohn's advice is not to fight the tool: use the tracker's word and keep the idea. It is not a category. "Reporting" or "Performance" groups tickets that share a subject and never finishes: that is a label, or what Cohn calls a theme. It is not a place to park ideas either. Shape Up's answer to a raw idea is "interesting, maybe some day", and no ticket. ## The two ways an epic fails you - **It never ends.** It began as a goal and became a bucket: new tickets are added as fast as old ones close. GitLab's handbook warns of epics that drag on indefinitely, and Shape Up calls the cause a grab-bag, several unrelated things under one name. - **Its tickets close and nothing works.** The work was divided by layer or by person, every piece is complete, and the pieces only meet at the end. Or the count of closed tickets rises while the hard question stays unanswered, and nobody reading the epic can tell. ## The title Name the result, so a reader of a roadmap knows what will exist. "Invoices can be exported and emailed", "Offline mode for the mobile app". Not the subject ("Invoice improvements") and not the activity ("Invoice work, phase 2"). ## The body In this order. Most of it is short. 1. **The goal, and why now.** The problem, for whom, and what they do today without this. Shape Up asks for one specific story that shows why the present state does not work. Linear's team calls the purpose of a project write-up situational awareness: in what context this was a good idea. 2. **What done means for the whole.** A few statements of what the product does when the epic is finished, written as functionality, the same way as a story's acceptance criteria. Where the work has stages, give each stage its own definition. Linear uses milestones for exactly this: done for a closed beta is not done for a public release. 3. **The shape of the solution, if one is agreed.** The main elements in a few lines, and a link to the specification or design document that holds the rest. 4. **What is left out.** Malte Ubl's definition of a non-goal is the useful one: not a negated goal, but something that could reasonably have been a goal and was chosen not to be. 5. **Known risks and open questions.** The parts nobody yet knows how to do. Shape Up calls them rabbit holes and wants them named before work starts. 6. **The children**, linked, in the order they will be done. Everything the epic does not name stays as it is. That holds for every ticket and is never written as a line of its own. ## Where the design lives The epic says what and why, within what bounds. How the system will be built, and the trade-offs behind it, go in a design document. Google's practice, as Ubl describes it, is that the design document is the place for the trade-offs and the alternatives considered. Linear's team writes a short specification of one or two pages with the key product and technical decisions. Keep that document with the code where the tools allow, link it from the epic, and put on the epic only the decisions a reader of the epic needs: what was chosen, and what it rules in or out. ## Breaking it down This is most of the work of an epic, and where most of them go wrong. - **See the whole before cutting it.** Jeff Patton lays the work out as a map: what the user does, in the order they do it, left to right, with the detail of each step beneath it. A flat list of tickets loses that shape, and with it the ability to see what is missing. - **Cut along what can be finished alone.** Shape Up's rule is to organise by the structure of the problem, not by person or role. Each piece cuts through every layer it needs, and can be finished, checked and shown without the others. A list for "backend" and a list for "frontend" produces tasks that are all done while nothing can be tried. - **First, the thinnest thing that works end to end.** Patton takes the top item under each step of the map and builds that first: the walking skeleton, Alistair Cockburn's term, which Patton describes as the smallest possible system that gives end-to-end functionality. Everything after it improves something that already runs. - **Then the piece that teaches the most.** Shape Up's test for what to start with: it is core to the idea, small, and new to the people building it. Push the parts with unknowns forward, and leave the routine parts for later, because an unknown found late can change everything built before it. - **Mark what could be cut.** Separate the must-haves from the nice-to-haves when the tickets are written, so it is clear what the goal can do without. - **Write only the near tickets in full.** GitLab's guidance is not to break work down far ahead of doing it. Shape Up's reason is that tasks imagined before the work starts are worse than tasks discovered by doing it. Give the next pieces full tickets, and the later ones a line each. - **Each child stands alone.** It has its own title, reason and done-when, and can be understood without opening the epic. It links back. Authors differ on one point. Atlassian suggests splitting an epic by the ordered steps of a process, or by user role. Humanizing Work and Shape Up warn against splitting by step. Both are right about different steps. The steps a user takes are good seams: "choose a plan", then "pay", then "get a receipt". The steps a builder takes are not: "schema", "API", "screen". Two questions check a breakdown: > If every child were closed, would the goal be met? > > Does every child serve the goal? A "no" to the first means a ticket is missing. A "no" to the second means a ticket belongs somewhere else. Shape Up allows a short list for loose ends and treats more than three to five items on it as a sign that a piece has not been named. If the pieces fall into groups that could each be finished and shipped without the others, it is several epics. Split it, and give each its own goal and definition of done. ## After it is filed An epic lives longer than any of its tickets, so keeping it true matters more. - **The description is the current plan.** When scope or design changes, edit the description and say in a comment what changed and who decided. A reader should never have to replay the history to learn what the epic is today. - **Post a status update when the state of the whole changes.** A piece is finished, a question is answered, a risk appears, work stops or starts again. Each update says three things: where the epic stands; what changed since the last one; and what comes next or is worrying. It is written for someone who is not doing the work. Linear's teams also give each update a health mark, which is worth copying where the tracker has one. - **Report what is unknown, not how many tickets are closed.** Shape Up's point is that a count of tasks says nothing about the tasks not yet discovered. Say which pieces are still being figured out and which only need doing. "We do not yet know how to do the sync, and that is the risk" is a good update. - **Progress on a piece goes on that piece.** The epic's update sums up. It does not repeat each child's comments. - **Cut scope against the baseline, not the ideal.** Shape Up's test for whether a piece can go: is what exists already better than what people have today? Record each cut on the epic, with where it went: a later epic, a ticket in the backlog, or nowhere. - **Adding scope is a decision, with a name on it.** New work found on the way either serves the goal or belongs elsewhere. - **Say when it is parked.** If work on the epic stops for now, write that on it, with what is finished and what the next step would be, so it can be picked up cold. ## Closing it - **Close against the definition of done**, not when the tickets run out. Say that each statement holds and how it was checked. - **List what was cut and where it went.** - **Leave no open children.** Finish them, move them, or close them with a reason. - **Link what shipped**: the release, the documentation, the announcement. - **Do not reopen it for follow-up work.** That is a new ticket, or a new epic. ## What does not belong on the epic The epic holds the goal, the bounds, the decisions and the state of the whole. It is tempting to make it the project's notebook, because it is the one ticket everyone opens. | The note | Where it goes | | --- | --- | | Goal, done, what is left out, decisions and who made them, current status | The epic | | Progress, questions and results for one piece | That child ticket | | How the system will be built, the trade-offs, the alternatives considered | A design document, linked from the epic | | A decision that shapes the structure of the system | A decision record in the repository | | Why a change is built the way it is, and how it was tested | The commit message or the pull request description | | What was tried along the way, meeting by meeting or session by session | Your own working notes, or nowhere | Michael Nygard's reason for keeping decisions as short records beside the code is that they are then versioned with what they describe. Simon Willison takes the other side and keeps his whole working record in the issue thread, which he calls controversial himself. A question settles most cases: > Would someone who will never read the code need this? If yes, it goes on the epic, in their terms. If no, it goes with the design or the change. ## Reviewing an epic Ask of each one: 1. Does the title name a result? 2. Can you say what the product does when it is finished, and is that written down? 3. Does it say what is left out? 4. Could each child be finished and shown alone? 5. Is there an early child that makes the thing work end to end? 6. If every child were closed, would the goal be met, and does every child serve it? 7. Are the unknowns named, and are they early in the order? 8. Does the description match today's plan, and does the last status update match the state of the work? 9. Is there anything on it that belongs on a child, in a design document or with the code? A "no" to 2 means it is a category, not an epic. A "no" to 4 means the work was cut by layer. ## Sources Read in November 2026. Check the current pages before quoting them. - Linear, "How we run projects at Linear" (the guiding sentences; projects have an end; short specifications and their purpose; status updates written by a project lead; milestones as staged definitions of done) and the Linear documentation, "Updates" (health as on track, at risk or off track, with a written description). - Ryan Singer, *Shape Up*: "Set Boundaries" (grab-bags; no backlog for raw ideas), "Write the Pitch" (problem, solution, rabbit holes, no-gos), "Get One Piece Done" (one integrated piece early; core, small and novel), "Map the Scopes" (organise by structure; imagined and discovered tasks; the loose-ends list), "Show Progress" (unknown against solved instead of task counts) and "Decide When to Stop" (compare to baseline; must-haves and nice-to-haves). - Jeff Patton, "The New User Story Backlog is a Map" (the map of activities and tasks; why a flat backlog loses the picture; the walking skeleton first, credited to Alistair Cockburn). - Mike Cohn, "Epics, Features and User Stories" (an epic is a big story; a theme is a group; use the tool's terms). - Atlassian, "Epics" (a body of work broken into stories; ways to break one down). - GitLab Handbook, "Using GitLab to plan work" (epics that drag on indefinitely; do not break work down far ahead; comment when closing). - Malte Ubl, "Design Docs at Google" (goals and non-goals; the design document as the place for trade-offs and alternatives). - Humanizing Work, "The Humanizing Work Guide to Splitting User Stories" (vertical slices; why splitting by layer fails). - Michael Nygard, "Documenting Architecture Decisions"; Simon Willison, "The Perfect Commit" (where decisions and working notes are kept, and the opposing view).