--- title: Manage scheduled tasks in Dispatcher Workspace description: As a dispatcher, you can move scheduled tasks to the Assigned state or move them back to the Pending dispatch state in Dispatcher Workspace. locale: en-US canonical_url: https://www.servicenow.com/docs/r/australia/field-service-management/field-service-scheduling/scheduled-tasks-workspace.html release: australia product: Field Service Scheduling classification: field-service-scheduling topic_type: task last_updated: "2026-03-12" reading_time_minutes: 1 breadcrumb: [Working on scheduled tasks, Using Dispatcher Workspace, Assigning tasks from Dispatcher Workspace, Scheduling and dispatching, Use, Field Service Management] --- # Manage scheduled tasks in Dispatcher Workspace As a dispatcher, you can move scheduled tasks to the Assigned state or move them back to the Pending dispatch state in Dispatcher Workspace. ## Before you begin Role required: wm\_dispatcher or wm\_crew\_moderator ## Procedure 1. Navigate to **All** > **Field Service** > **Dispatching** > **Dispatcher Workspace**. 2. View the list of all scheduled tasks, including crew tasks, in the dispatcher group by selecting **Scheduled Tasks** in the Tasks filter. 3. Assign or update a scheduled task.
Option Steps
**Assign a scheduled task** 1. Select a task card or a calendar event. 2. Select the overflow icon. 3. Select **Confirm Assignment**. 4. Select **Save**.
**Unassign a scheduled task** 1. Select a calendar event. 2. Select the overflow icon. 3. Move a scheduled task to the Pending dispatch state by selecting **Unassign task**.
**Reschedule a scheduled task** 1. Drag and drop a scheduled task to a different time slot on the calendar. 2. Select the **Set to 'Assigned'** check box. **Note:** This option appears only if the scheduled task starts beyond the 12-hour threshold.
**Edit the duration of a scheduled task** 1. Move to the side of the calendar event bar. 2. Select and drag to adjust the start or end time of a task. **Note:** The travel duration won’t be affected.
**Remove time gaps between tasks** 1. Select and hold \(or right-click\) on a task in the calendar. 2. Select **Remove time gap**. **Note:** This feature is restricted when: - The task is the first of the day. - The task's status is in progress, closed complete, or canceled.