--- title: Pre-date a project task description: Move the planned start date of a task before the planned start date of a project. Adding a pre-dated task allows you to accommodate tasks which need to start before the planned start date of a project. locale: en-US canonical_url: https://www.servicenow.com/docs/r/australia/it-business-management/project-management/pre-date-prj-dt.html release: australia product: Project Management classification: project-management topic_type: task last_updated: "2026-09-07" reading_time_minutes: 1 breadcrumb: [Change the planned start date of a project, Starting a project, Using Project Management, Project Management, Project Portfolio Management, Strategic Portfolio Management] --- # Pre-date a project task Move the planned start date of a task before the planned start date of a project. Adding a pre-dated task allows you to accommodate tasks which need to start before the planned start date of a project. ## Before you begin You should have created or added project tasks to your project. Role required: it\_project\_manager ## About this task Before pre-dating a project task, note the following conditions: - The property project.rollup\_project\_start\_date should be set to true. - Pre-dating a task's planned start date also moves the project's planned start date. - The start date of a child task can't be moved before the parent task's start date. For example, a parent task with Start no earlier than constraint starts on the 20th and the child task starts on the 30th. The start date of the child task can only be moved up to the 20th. ## Procedure 1. Navigate to **All** > **Project** > **Projects** > **All**. 2. Select the project from the list. 3. On the Project form, update the planned start date for a project task using either of the following options.
| Option | Steps |
|---|---|
| **From the Project Task form** | 1. In the Project Tasks related list, select the project task which you want to pre-date. 2. On the Project Task form, select the **Dates** tab and update the **Planned start date** for the task. |
| **From the Planning Console** | 1. On the Project form, select the **Planning Console** related link. 2. In the Planning Console, update the start date of the project task under the **Planned start date** column. |