--- title: Predecessor dependencies in the planning console description: In the WBS section of the planning console, you can create dependencies between tasks by specifying a series of values. locale: en-US canonical_url: https://www.servicenow.com/docs/r/australia/it-business-management/project-management/r\_ProjectTaskDependencyValues.html release: australia product: Project Management classification: project-management topic_type: reference last_updated: "2026-03-12" reading_time_minutes: 2 breadcrumb: [Using Planning console - Legacy, Using Project Management, Project Management, Project Portfolio Management, Strategic Portfolio Management] --- # Predecessor dependencies in the planning console In the WBS section of the planning console, you can create dependencies between tasks by specifying a series of values. The **Predecessor** column on the planning console can specify dependencies between tasks. The values that you put in this column must be in the following format: `{WBS_number}{dependency_type}+{lag_time}` Where - `WBS_number` is the number of the predecessor task in the relationship. - `dependency_type` is one of the [types of dependencies](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/australia/markdown/australia/it-business-management/project-management/c_ParentChildRollupTaskCalcs.md) that the application supports. - `lag_time` is the amount of time, in days, to delay the start of the dependent task. This value can be positive or negative integers. The values are entered without the curly braces \{\}. See the examples in the table. **Note:** You can also edit tasks from the Gantt chart by clicking the relationship line. See [Gantt chart options](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/australia/markdown/australia/it-business-management/project-management/r_EditTasks.md) and [Modify a project task dependency](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/australia/markdown/australia/it-business-management/project-management/t_ModifyProjectTaskDependencies.md) for details. |Dependency type|Example|Additional information| |---------------|-------|----------------------| |Finish to start|**1.1fs+0**|The task you are editing starts when task 1.1 is finished.| |Start to start|**1.1ss+0**|Task 1.1 cannot finish until the task you are editing finishes.| |Start to finish|**1.1sf+0**|Task 1.1 cannot start until the task you are editing finishes.| |Finish to finish|**1.1ff+0**|The task you are editing cannot finish until task 1.1 finishes.| **Parent Topic:**[Using Planning console - Legacy](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/australia/markdown/australia/it-business-management/project-management/c_TheProjectPlanningConsole.md) **Related topics** [Open the project planning console]() [Planning console tasks]() [Client side planning console]() [Gantt chart]() [Create a parent-child relationship on the planning console]() [Custom columns in the planning console]() [Create a dependency from the planning console]() [Using Planning console - Legacy](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/australia/markdown/australia/it-business-management/project-management/c_TheProjectPlanningConsole.md)