--- title: Recalculating costs of all resource plans in a project description: Recalculate resource costs for all resource plans in a project when hourly rates change in the associated rate model. locale: en-US canonical_url: https://www.servicenow.com/docs/r/australia/it-business-management/project-management/recalculate-resource-costs-of-a-project.html release: australia product: Project Management classification: project-management topic_type: task last_updated: "2026-09-08" reading_time_minutes: 5 breadcrumb: [Starting a project, Using Project Management, Project Management, Project Portfolio Management, Strategic Portfolio Management] --- # Recalculating costs of all resource plans in a project Recalculate resource costs for all resource plans in a project when hourly rates change in the associated rate model. ## Before you begin Ensure the following setup: - The project must be active. - The project must have an active rate model assigned. - The resource plans must be in the Planned, Requested, Confirmed, or Allocated state. Role required: project\_manager ## About this task This option recalculates the costs of all resource plans of the project at once. You can also open a resource plan from the **Resource Plans** related list to [recalculate the resource costs of an individual resource plan](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/australia/markdown/australia/it-business-management/resource-management/recalculate-resource-costs.md). ## Procedure 1. Navigate to **All** > **Project** > **Projects** > **All**. 2. Open a project. 3. On the Project form, right-click on the header bar and select the **Recalculate Resource Costs** option. 4. In the Recalculate Resource Cost dialog box, fill in the fields.
| Field | Description |
|---|---|
| Start date | Start date of the time period for which the costs are recalculated.By default, the field shows the current date. |
| End date | End date of the time period for which the costs are recalculated.By default, the field shows the end date of the project. |
| Planned costs for Requested Resource plans | Option for recalculating the planned cost of Requested resource plans. |
| Confirmed/Allocated costs for Confirmed/Allocated resource plans | Option for recalculating the confirmed or allocated cost of Requested resource plans. |
| Planned costs for Confirmed/Allocated resource plans | Option for including the planned cost of a Confirmed or Allocated plan.The option is enabled if the **Confirmed/Allocated costs for Confirmed/Allocated resource plans** option is selected. By default, the option is not selected. |