--- title: Task link types description: Task links define the dependency relationship between tasks. Linking tasks creates dependencies that affect task start and finish dates and determine the critical path. The following table describes the four supported link types. locale: en-US canonical_url: https://www.servicenow.com/docs/r/australia/it-business-management/project-management/task-link-types-project-management.html release: australia product: Project Management classification: project-management topic_type: reference last_updated: "2026-03-18" reading_time_minutes: 1 breadcrumb: [Project Management reference, Project Management, Project Portfolio Management, Strategic Portfolio Management] --- # Task link types Task links define the dependency relationship between tasks. Linking tasks creates dependencies that affect task start and finish dates and determine the critical path. The following table describes the four supported link types. |Link type|Abbreviation|Description| |---------|------------|-----------| |Finish-to-Start|FS|Task B cannot start until Task A finishes.| |Start-to-Start|SS|Task B cannot start until Task A starts.| |Finish-to-Finish|FF|Task B cannot finish until Task A finishes.| |Start-to-Finish|SF|Task B cannot finish until Task A starts.| **Related topics** [Assign a project schedule](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/australia/markdown/australia/it-business-management/project-management/t_UseAProjectSchedule.md) [Project scheduling in Project Management](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/australia/markdown/australia/it-business-management/project-management/project-schedules-tasks.md)