--- title: Add internal project task dependencies from Project Workspace description: Create dependencies between project tasks using the interactive UI of Project Workspace. locale: en-US canonical_url: https://www.servicenow.com/docs/r/australia/it-business-management/project-workspace/create-dependencies-for-project-tasks-from-project-workspace.html release: australia product: Project Workspace classification: project-workspace topic_type: task last_updated: "2026-09-10" reading_time_minutes: 1 breadcrumb: [Manage projects, Project Workspace, Project Portfolio Management, Strategic Portfolio Management] --- # Add internal project task dependencies from Project Workspace Create dependencies between project tasks using the interactive UI of Project Workspace. ## Before you begin Verify that you have the Dependency Lines toggle enabled on the settings of the timeline. For information on how to update the settings, see [Personalize the planning page view in Project Workspace](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/australia/markdown/australia/it-business-management/project-workspace/personalize-planning-console-in-project-workspace.md). Role required: it\_project\_manager ## Procedure 1. Select a project to open it from the planning page. For information on how to navigate to the planning page, see [Access the Project Workspace](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/australia/markdown/australia/it-business-management/project-workspace/access-new-project-workspace.md). 2. Create task dependencies in one of the following ways.
Option Action
**From the data grid** Use the dependency type-ahead feature. 1. Double-click \(or use the keyboard shortcut\) the dependency cell of the project task. 2. Select the task to set as a dependency to this task. 3. Select the type of dependency to be applied. 4. Select the lag period to be applied to the dependency.
**From the timeline view** Draw a dependency line. 1. Place the cursor on the task bar for which you want to create the dependency. 2. Draw a line from the circle on one end of the bar and drop it on the circle of the dependent task bar.
The created dependency is shown as a line between the two task bars, on the timeline view. ## What to do next You can edit the dependency. For more information, see [Update task dependency details from Project Workspace](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/australia/markdown/australia/it-business-management/project-workspace/update-the-dependency-details-for-tasks-from-project-workspace.md). - **[Update task dependency details from Project Workspace](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/australia/markdown/australia/it-business-management/project-workspace/update-the-dependency-details-for-tasks-from-project-workspace.md)** Update the details of the dependency including its type and lag time from Project Workspace. **Parent Topic:**[Managing projects with Project Workspace](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/australia/markdown/australia/it-business-management/project-workspace/use-projects-pw.md)