--- title: Legacy: State model and transitions description: Change Management offers a state model to move and track change requests through several states. locale: en-US canonical_url: https://www.servicenow.com/docs/r/australia/it-service-management/change-management/c\_ChangeStateModel.html release: australia product: Change Management classification: change-management topic_type: concept last_updated: "2026-03-12" reading_time_minutes: 5 breadcrumb: [Configure, Change Management, IT Service Management] --- # Legacy: State model and transitions Change Management offers a state model to move and track change requests through several states. **Note:** The change states functionality has been replaced with change models since the Quebec release. For more information, see [Create a Change model](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/australia/markdown/australia/it-service-management/change-management/create-a-change-model.md). \[Omitted image "change-state-model.png"\] Alt text: State transitions in a normal change request The following table provides a list of all the states that a change request can progress through. Email notifications can be sent to the user who requested the change when it progresses to the following states: **Scheduled**, **Implement**, **Review**, and **Canceled**.
State Description State value
New Change request is not yet submitted for review and authorization. A change requester can save a change request as many times as necessary while building out the details of the change prior to submission. -5
Assess Peer review and technical approval of the change details are performed during this state. -4
Authorize Change Management and the CAB schedule the change and provide final authorization to proceed. -3
Scheduled The change is fully scheduled and authorized, and is waiting for the planned start date. An email notification is sent to the user who requested the change. -2
Implement The planned start date has approached and the actual work to implement the change is being conducted. An email notification is sent to the user, who requested the change. -1
Review The work has been completed. The change requester determines whether the change was successful. A post-implementation review can be conducted during this state. An email notification is sent to the user who requested the change.**Note:** You cannot cancel the change request if it is in the Review state. 0
Closed All review work is complete. The change is closed with no further action required. 3
Canceled A change can be canceled at any point when it is no longer required. However, a change cannot be canceled from a **Closed** state. An email notification is sent to the user who requested the change. 4
Normal, standard, and emergency changes progress through states in different ways. ## State progress for different changes - Normal changes progress through all states. - Standard changes are considered to be pre-authorized, so they bypass the **Assess** and **Authorize** states that trigger approval records. Approving these changes progress the change to the next appropriate state. Rejecting these changes send them back to **New** state. - Emergency changes are similar to standard changes, except that they must be authorized. ## Revert a change request to a New change Change Management allows the Emergency and Normal change types to be reverted to the new state which is the first approval state using the **Revert to New** action from the **Context** Menu. This action is performed if the approval was requested and the submitter recognizes that not all configuration item in the scope of the change is included before submitting for approval. - To modify the Normal change request to the New state, modify the state of a change request from **Assess** state to **New** state by clicking **Revert to New** from the Context menu. - To modify the Emergency change request to the New state, modify the state of a change request from **Authorized** state to **New** state by clicking **Revert to New** from the Context menu. **Note:** When you revert to **New** from the **Assess** state or the **Authorized** state, the workflow is restarted and all pending approvals are cancelled. ## Modify change request type - A new ACL for change\_request.type has been added that allows modification of the **Type** field in change request when the change request is in a **New** state and no approvals have been generated yet for it. - In case of **Standard** change request, you can modify the type of the change request from Standard to **Normal** or **Emergency**, if the state of a change request is **New**. - In case of **Normal** or **Emergency** change request, you can modify the type of the change request from **Normal** to **Emergency** or vice versa if the state of a change request is **New**. - If a **Normal** or **Emergency** change request is rejected, the state of the change request is set to **New**. As the state of the change request is **New**, you can modify the type of the change request again. For example, if your **Emergency** change request is rejected on the grounds that the change request is **Normal**, you can modify the **Type** of the change request to **Normal** and resubmit the change request. ## Disabled Cancel change action The Cancel option for a change request in the Review state is disabled. This restricts cancelling the request when the work is complete and is waiting for review. ## Change model attributes The Change Manager has the option to mandate specific actions when a Change Request is moved to a specific state. Attributes assigned to that state determine what actions can take place. By default, there are two attributes to manage a change request: - allow\_ci\_modification – Allows to modify the CI. Attributes are only considered if they are included in a model. If the `allow_ci_modification` attribute is not added to a model, it defaults to its initial state. - allow\_implementation – Indicates that the change will be implemented. By enabling `allow_implementation`, this feature replaces the implementation states field currently present on the Change model. Both the states listed in the implementation states field and the attribute will be respected. - **[Legacy: Add a state to the state model](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/australia/markdown/australia/it-service-management/change-management/t_AddANewState.md)** You can add a new state to the existing state model for different change types based on the requirements of your organization. - **[Configure state model transitions](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/australia/markdown/australia/it-service-management/change-management/t_ConfigStateModelTransit.md)** You can use script includes or UI policies to configure state models and the criteria for moving change requests from one state to another. **Parent Topic:**[Configuring Change Management](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/australia/markdown/australia/it-service-management/change-management/configure-change-management.md)