--- title: Resource assignment offsets in demand-based projects description: When you create a project from a demand, resource assignments keep their start dates, and the offset is recalculated in working days based on the project schedule. locale: en-US canonical_url: https://www.servicenow.com/docs/r/it-business-management/project-workspace/demand-project-offsets.html release: brazil product: Project Workspace classification: project-workspace topic_type: concept last_updated: "2026-10-01" reading_time_minutes: 2 keywords: [resource assignment, offset, demand, project schedule, working days, Project Workspace] breadcrumb: [Create a project from Project Workspace, Manage projects, Project Workspace, Project Portfolio Management, Strategic Portfolio Management] --- # Resource assignment offsets in demand-based projects When you create a project from a demand, resource assignments keep their start dates, and the offset is recalculated in working days based on the project schedule. ## How offsets work The Offset field on a resource assignment shows the difference, in days, between the project or task start date and the resource assignment start date. A demand has no schedule, so the offset on a demand counts every day, including Saturdays and Sundays. A project has a schedule, so the offset on a project counts only the working days defined in that schedule. When you create a project from a demand, the resource assignments keep their start dates, and the offset is recalculated for the project. This behavior applies when you select **Create Project** in the Related Links of a demand. ## Key benefits This behavior provides the following benefits: - Resource assignments start on the dates that were planned in the demand. - Weekends and holidays that the demand didn't account for don't push assignments to later dates. - The offset matches how the project schedule counts time, so the dates and the offset stay consistent. ## How it works When a demand is converted to a project, the following happens: 1. Each resource assignment keeps its start date. 2. The offset is recalculated as the number of working days between the project start date and the assignment start date. 3. The working days are calculated from the defined schedule in the **Schedule** field of the project. For example, a demand and its project both start on August 3, and a resource assignment starts on August 17. The offset for the same assignment is shown in the following table. |Record|Assignment start date|Offset|Days counted| |------|---------------------|------|------------| |Demand|August 17|14 days|Every day| |Project|August 17|10 days|Working days in the project schedule| The assignment keeps its start date. The offset drops from 14 to 10 because the two weekends between August 3 and August 17 aren't counted. ## Considerations Consider the following when you work with offsets in projects created from a demand: - Holidays and other non-working days that are defined in the schedule aren't counted in the offset. - The Schedule field of the project is populated with a default schedule, Project Management Schedule, in which the working days are Monday to Friday. The default schedule can be replaced with a different one. **Parent Topic:**[Create a project from Project Workspace](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/brazil/markdown/it-business-management/project-workspace/create-project-from-project-workspace.md) **Related topics** [Resource assignment form](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/brazil/markdown/it-business-management/project-workspace/pw-resource-assignment-form.md) [Resource assignments in Project Workspace](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/brazil/markdown/it-business-management/project-workspace/resource-assignments-pw.md) [Assign a project schedule](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/brazil/markdown/it-business-management/project-management/t_UseAProjectSchedule.md)