# Dispute Resolution in Construction — Reference ## Table of Contents 1. [ADR Spectrum](#adr-spectrum) 2. [Negotiation & Mediation](#mediation) 3. [Adjudication](#adjudication) 4. [DAB / DAAB (FIDIC)](#daab) 5. [Arbitration](#arbitration) 6. [Conflict Avoidance Board (CAB)](#cab) 7. [Key Cases](#cases) 8. [Enforcement](#enforcement) --- ## ADR Spectrum {#adr-spectrum} | Method | Binding? | Speed | Cost | Formality | |--------|----------|-------|------|-----------| | Negotiation | No | Fast | Lowest | Informal | | Mediation | No (unless settled) | Fast | Low | Semi-formal | | Conciliation | Non-binding recommendation | Medium | Low-Medium | Semi-formal | | Conflict Avoidance Board | Parties decide | Ongoing | Medium | Structured | | Adjudication (statutory) | Temporarily binding | Very fast (weeks) | Medium | Formal | | DAB/DAAB | Binding (subject to NOD) | Medium | Medium-High | Formal | | Arbitration | Final & binding | Slow | High | Formal | | Litigation | Final & binding | Slowest | Highest | Most formal | --- ## Negotiation & Mediation {#mediation} ### Mediation in Construction - Facilitative process — mediator helps parties reach agreement, does not impose decision - **Cheapest ADR mechanism** available (Gillion) - Very high resolution rate at SMC (Singapore Mediation Centre) - Typically completed in **1–2 days**: position paper → mediator → workshop → plenary - Over 25 years of construction practice, **mediation is underused** - Non-binding unless parties sign settlement agreement ### When Mediation Works Best - Parties have ongoing relationship (want to preserve) - Dispute is commercial rather than purely legal - Both parties willing to compromise - Confidentiality important - Early in dispute lifecycle (before positions harden) ### When Mediation May Not Work - One party acting in bad faith - Significant power imbalance - Pure legal question requiring binding precedent - Party needs urgent interim relief --- ## Adjudication {#adjudication} ### Statutory Adjudication (Singapore SOP Act) - **Temporarily binding** — pay now, argue later - Designed for **cash flow** protection, not final resolution - Cannot be contracted out of (Section 36 SOP Act) ### Process 1. Payment claim served 2. Payment response due within 21 days 3. If dispute → adjudication application within 7 days 4. Adjudication response within 7 days 5. Adjudicator determines within 7–14 days 6. Payment within 7 days of determination ### Key Principles - **Respondent's payment response is critical** — failure to respond = "smash and grab" (respondent cannot raise withholding reasons) - Determination is temporarily binding — can be reopened in arbitration/litigation - Adjudicator's jurisdiction is narrow — only the payment claim in dispute - Multiple adjudications possible — fresh claims each payment cycle ### UK Adjudication (Housing Grants Act 1996) - Similar concept — 28-day determination - "Pay now, argue later" principle - Right cannot be contracted out of - Widely used in UK construction industry --- ## DAB / DAAB (FIDIC) {#daab} ### Evolution | Edition | Body | Type | |---------|------|------| | Pre-2017 | DAB (Dispute Adjudication Board) | Ad hoc or standing | | 2017 | DAAB (Dispute Avoidance/Adjudication Board) | **Standing** (mandatory for Red/Yellow) | ### 2017 DAAB — Dual Role 1. **Avoidance**: Regular site visits, early engagement, informal opinions 2. **Adjudication**: Formal binding decisions on referred disputes ### Referral to DAAB 1. Either party refers dispute after Engineer's determination (or failure to determine) 2. DAAB has **84 days** to decide (extendable by agreement) 3. Decision is **binding** — immediate compliance required 4. NOD within **28 days** → dispute can proceed to arbitration 5. No NOD → decision becomes **final and binding** ### Non-Compliance - 2017 clarification: non-compliance is a **separate dispute** - Can be referred **directly to arbitration** — no need to go back to DAAB - Can seek **partial award** for non-compliance while merits continue - Persero case (Singapore) confirmed this approach ### DAAB vs SMC CAB | Feature | FIDIC DAAB | SMC CAB | |---------|-----------|---------| | Primary role | Dispute resolution (reactive) | Dispute **avoidance** (proactive) | | Mediation? | No (unless separately agreed) | **Yes** — strong emphasis (Rule 7) | | Composition | 1 or 3 members | Default 1, flexible per issue | | Decision timeframe | 84 days | No fixed timeframe | | Site visits | Yes (standing DAAB) | Yes — predetermined agenda | | Binding? | Yes (subject to NOD) | Parties decide per issue | --- ## Arbitration {#arbitration} ### Key Features in Construction - **Final and binding** — limited grounds for challenge (procedural irregularity, public policy) - **Confidential** — unlike court proceedings - **Party autonomy** — parties choose arbitrators, procedure, seat, language - **Expert arbitrators** — can appoint construction specialists (unlike judges) - **International enforcement** — New York Convention (1958) ### Common Arbitral Institutions for Construction | Institution | Abbreviation | Base | |-------------|-------------|------| | Singapore International Arbitration Centre | SIAC | Singapore | | Singapore Institute of Arbitrators | SIArb | Singapore | | International Chamber of Commerce | ICC | Paris | | London Court of International Arbitration | LCIA | London | | Hong Kong International Arbitration Centre | HKIAC | Hong Kong | | Kuala Lumpur Regional Centre for Arbitration | AIAC | Kuala Lumpur | ### Seat vs Venue - **Seat** = legal jurisdiction governing the arbitration (procedural law) - **Venue** = physical location of hearings (can differ from seat) - Seat determines: court supervisory jurisdiction, enforcement regime, available challenges ### Singapore as Arbitration Seat - International Arbitration Act (IAA) — based on UNCITRAL Model Law - Minimal court intervention policy - Strong enforcement track record - Party to New York Convention - Preferred seat for Asia-Pacific construction disputes ### Multi-Party / Multi-Contract Arbitration - Common in construction (employer, contractor, subcontractors, consultants) - **Joinder**: bringing additional parties into existing arbitration - **Consolidation**: merging related arbitrations - Requires: arbitration agreement permitting joinder/consolidation, or institutional rules allowing it - SIAC Rules 2016: provisions for joinder and consolidation ### Interim Measures - Arbitral tribunal can grant interim relief (preservation of evidence, security for costs, injunctions) - Emergency arbitrator provisions available under most institutional rules - Court may also grant interim measures in support of arbitration --- ## Conflict Avoidance Board (CAB) {#cab} ### SMC Integrated ADR Framework - Standalone rules by Singapore Mediation Centre - Can be **plugged into any contract** — not tied to specific standard form - Combines dispute avoidance + mediation + determination ### Four Functions | Function | Description | Binding? | |----------|-------------|----------| | 1. Dispute Avoidance | Regular site meetings, risk monitoring, cooperation | N/A | | 2. Informal Assistance | Non-binding guidance on issues before they become disputes | Non-binding | | 3. Mediation (Rule 7) | Formal mediation — position papers, mediator, plenary | N/A (facilitative) | | 4. Opinion/Determination | Formal decision on referred disputes | Parties decide | ### Site Visit Agenda - Progress summary - Risk register update - Claims/issues status - Mitigation measures - Completion dates review ### Advantages - Proactive — prevents disputes from escalating - Flexible — parties choose binding or non-binding per issue - Cost-effective — cheaper than arbitration - Includes mediation — built-in facilitative process ### Limitations - Not widely adopted yet - Requires parties willing to engage in good faith - No established enforcement mechanism (unlike FIDIC DAAB) --- ## Key Cases {#cases} ### Persero (Singapore) - Indonesian construction project, arbitration seated in Singapore - Issue: must non-compliance with DAB decision be re-referred to DAB before arbitration? - **Held**: No — can go directly to arbitration - Significance: clarified enforcement of DAB/DAAB decisions globally ### Henry Boot v Malmaison [1999] (UK) - Concurrent delay case - **Held**: Contractor entitled to EOT if employer delay event would have caused delay regardless of concurrent contractor delay - Foundation of "Malmaison approach" to concurrent delay ### Walter Lilly v Mackay [2012] (UK) - Global claims case - **Held**: Global claims permissible where events and losses cannot be individually linked - Must show: causal connection exists; no claimant-fault events included ### Costain v Bechtel — Channel Tunnel Rail Link (UK) - NEC contract — Clause 10.1 (mutual trust and cooperation) - **Held**: Clause 10.1 imposes obligation of honesty and proper conduct - BUT does not override contract mechanism or create new rights - Good faith = guiding behaviour, not source of claims ### Yam Seng v ITC [2013] (UK) - First implied duty of good faith in relational/commercial contracts - **Later limited** by Quantum Advisory — good faith only for very specific contract forms ### Peak Construction v Wilson Homes [2001] (UK) - Prevention principle case - **Held**: If no EOT mechanism for employer-caused delay → time at large → LDs unenforceable --- ## Enforcement {#enforcement} ### Enforcing Arbitral Awards - **New York Convention (1958)**: Awards enforceable in 170+ countries - Limited grounds for refusal (Article V): procedural irregularity, lack of jurisdiction, public policy - Singapore: enforcement under IAA Section 19 or Arbitration Act Section 46 ### Enforcing Adjudication Determinations - Singapore SOP Act: determination enforceable as a judgment debt - If respondent fails to pay → claimant can apply for judgment - Court will enforce unless adjudicator lacked jurisdiction or breach of natural justice ### Enforcing DAAB Decisions - Binding immediately — must comply even if NOD issued - Non-compliance → refer to arbitration for enforcement (partial award) - No need to re-refer to DAAB (Persero)