# FIDIC 2017 Suite — Clause Reference ## Table of Contents 1. [Red Book (Conditions of Contract for Construction)](#red-book) 2. [Yellow Book (Conditions of Contract for Plant & Design-Build)](#yellow-book) 3. [Silver Book (Conditions of Contract for EPC/Turnkey)](#silver-book) 4. [Emerald Book (Conditions of Contract for Underground Works)](#emerald-book) 5. [Key Clauses Across All Books](#key-clauses) 6. [Time-Bars & Notice Requirements](#time-bars) 7. [DAAB Procedures](#daab) 8. [2017 vs Pre-2017 Changes](#changes) --- ## Red Book ### Risk Allocation - **Employer** bears: quantity risk, unforeseeable ground conditions, employer's design errors, force majeure (shared) - **Contractor** bears: rate risk, workmanship, programme, resources, subcontractor management ### Key Clauses | Clause | Subject | Key Points | |--------|---------|------------| | 1.1.29 | Cost | Defined as expenditure reasonably incurred (or to be incurred), including overhead but NOT profit | | 1.1.80 | Time for Completion | Date/period stated in Contract Data | | 4.12 | Unforeseeable Physical Conditions | Contractor entitled to EOT + Cost + Profit if unforeseeable | | 8.4 | EOT | Contractor entitled if delayed by listed causes; must give notice under 20.2 | | 8.8 | Delay Damages | Employer entitled to LDs per Contract Data | | 13.1 | Right to Vary | Engineer may initiate; Contractor must comply unless unable | | 13.3 | Variation Procedure | Instruction → Contractor proposes → Engineer responds | | 14.3 | Interim Payment | Monthly applications; Engineer certifies within 28 days | | 14.6 | IPC Issuance | Engineer issues IPC within 28 days of receiving Statement | | 15.1 | Notice to Correct | Employer may give notice if Contractor fails obligations | | 15.2 | Termination by Employer | 14 days notice after Notice to Correct not complied | | 16.1 | Suspension by Contractor | If Employer fails to pay within 42 days of IPC due date | | 16.2 | Termination by Contractor | 14 days notice for listed defaults | | 17.2 | Indemnities | Mutual indemnities for death/injury and property damage | | 18.1 | Exceptional Events | Force majeure equivalent; both parties may claim EOT | | 20.1 | Claims (Contractor) | 28-day notice requirement from awareness | | 20.2 | Claims Procedure | Detailed procedure for notices and substantiation | | 21 | Disputes | DAAB standing board; 28 days for decision | ## Yellow Book ### Key Differences from Red Book - **Contractor designs** based on Employer's Requirements - **Fitness for purpose** obligation (higher than reasonable skill & care) - **Employer's Requirements** replace Drawings/Specifications - Contractor bears **design risk** — errors in Employer's Requirements may still be Contractor's risk if discoverable - Clause 5.1: Contractor's design obligation — must satisfy Employer's Requirements - Clause 5.8: Design errors — Contractor responsible for errors in design documents ### Design Liability - Standard of care: **fitness for purpose** (unless amended) - Contractor must check Employer's Requirements for errors/defects — Clause 5.1 - If Contractor discovers error → must notify Engineer (Clause 5.1) - If Contractor fails to discover error it should have found → Contractor's risk ## Silver Book ### Key Differences - **Maximum risk transfer** to Contractor - No Clause 4.12 (unforeseeable physical conditions) — Contractor deemed to have allowed for all conditions - No Clause 18 exceptional events relief in some versions - No Engineer role — replaced by Employer's Representative (or Employer administers directly) - Lump sum pricing — no re-measurement - Contractor bears risk of: ground conditions, design, errors in Employer's Requirements ### When to Use - Well-defined scope with experienced contractor - Employer wants price certainty - BOT/PPP/concession projects - Risk: good contractors may avoid bidding; weak contractors underprice then claim ## Emerald Book ### Tunnelling-Specific Provisions - **Geotechnical Baseline Report (GBR)** — defines expected ground conditions - Conditions worse than GBR → Employer's risk - Conditions better than GBR → Employer benefits (cost savings shared) - Specific provisions for TBM (tunnel boring machine) operations - Changed conditions mechanism tailored for underground works --- ## Key Clauses Across All Books {#key-clauses} ### Clause 20.2 — Claims (2017 Edition) **Notice requirement**: 28 days from date the Contractor became aware (or should have become aware) of the event/circumstance. **Procedure**: 1. **Notice of Claim** — within 28 days (time-bar) 2. **Fully detailed claim** — within 84 days of Notice, or as agreed 3. **Engineer's initial response** — within 42 days 4. **Engineer's determination** — if parties cannot agree **Time-bar effect**: Failure to give 28-day notice → claim deemed time-barred. BUT: - 2017 edition added Clause 20.2.7: Engineer must notify Contractor if notice was late - If Engineer fails to notify → time-bar may not apply (debated) ### Clause 3.7 — Engineer's Determination (2017) - Engineer must act **neutrally** (not as Employer's agent) when making determinations - Must consult both parties before determining - 42-day time limit for determination - New in 2017 — strengthens Engineer's independence ### Clause 14.7 — Payment (2017) - Employer must pay within **56 days** of receiving Statement (if no IPC issued) - Late payment → financing charges (Clause 14.8) - Non-payment → Contractor may suspend (Clause 16.1) or terminate (Clause 16.2) --- ## Time-Bars & Notice Requirements {#time-bars} | Event | Notice Period | Clause | Consequence | |-------|--------------|--------|-------------| | Contractor's claim | 28 days from awareness | 20.2.1 | Time-barred if late | | Employer's claim | 28 days from awareness | 20.1 | Time-barred if late | | Fully detailed claim | 84 days from Notice | 20.2.4 | Claim may be reduced | | Variation proposal | As instructed | 13.3 | — | | Unforeseeable conditions notice | As soon as practicable | 4.12 | Entitlement affected | | Notice to Correct | Reasonable period | 15.1 | May lead to termination | | Dispute referral to DAAB | 28 days after Engineer's determination (or failure) | 21.4 | Lose right if not referred | | NOD (Notice of Dissatisfaction) | 28 days after DAAB decision | 21.4.4 | Decision becomes final & binding | --- ## DAAB Procedures (2017) {#daab} ### Standing DAAB - Appointed at commencement (Red/Yellow) — not ad hoc - Regular site visits, predetermined agenda - Available throughout project life ### Referral Process 1. Either party refers dispute to DAAB 2. DAAB has **84 days** to give decision (extendable) 3. Decision is **binding** — must be complied with immediately 4. If no NOD within 28 days → decision becomes **final and binding** ### Non-Compliance with DAAB Decision - **2017 clarification**: Non-compliance = separate dispute → refer directly to arbitration - No need to re-refer to DAAB first (Persero case confirmed this for Singapore) - Can seek **partial award** in arbitration for non-compliance ### Persero Case (Singapore) - Indonesian construction project, arbitration seated in Singapore - Court of Appeal to Supreme Court - Held: party can go directly to arbitration for non-compliance — no need to go back to DAAB - Landmark case for FIDIC dispute resolution --- ## 2017 vs Pre-2017 Key Changes {#changes} | Feature | Pre-2017 | 2017 Edition | |---------|----------|-------------| | Engineer's role | Agent of Employer | Must act **neutrally** on determinations (3.7) | | DAAB | Ad hoc or standing (DAB) | **Standing DAAB** mandatory (Red/Yellow) | | Notice of Claim | 28 days (strict time-bar) | 28 days + Engineer must notify if late (20.2.7) | | Advance Warning | Not explicit | **Early Warning** mechanism added | | Non-compliance enforcement | Unclear | Direct referral to arbitration confirmed | | Variation by Employer | Less structured | More detailed procedure (13.3) | | Programme | Less emphasis | Detailed programme requirements (8.3) |