# Claims Management Framework — Refinery/Petrochem EPC ## Claim Types (Frequency in Pakistan EPC Projects) | Type | Frequency | Typical Quantum | |---|---|---| | **Variation (Scope Change)** | High | 10-30% of CP | | **Force Majeure (FX, supply chain)** | Med | Time-only typically | | **Unforeseeable Site Conditions** | Med | 2-10% of CP | | **Employer-Caused Delay** | Med | 1-5% of CP + acceleration | | **Disruption / Loss of Productivity** | Med | 3-15% of disrupted scope | | **Acceleration** | Low-Med | Direct cost + 20-30% margin | | **Termination & Compensation** | Low | NBV + reasonable profit | | **Quantum Meruit (illegal contract)** | Rare | Reasonable value of work done | ## Time-Bar Discipline — The 28-Day Clock **FIDIC 2017 Sub-Clause 20.2.1**: Contractor's claim is **time-barred** if notice not given within 28 days of event becoming known. **Watershed: 2017 vs 1999 difference** - 1999: Some jurisdictions held 28-day clause as "notice of intention only"; tribunals sometimes admitted late claims - 2017: Clearer time-bar drafting; tribunals (especially Pakistan, SE Asia) increasingly enforcing strictly **Practical protocol**: 1. Claims register on Day 1 of contract 2. Weekly "claims sweep" by Contract Manager — every event documented to prevent slipping past 28 days 3. Conservative bias: "When in doubt, notice it" — notice is cheap; claim preparation comes later 4. Use standard claim notice template embedded in PMC system ## Quantum Calculation Methodologies ### 1. Cost-Reimbursement Method (Direct Cost) - Labor hours × labor rate (audited timesheets) - Materials cost (invoices + freight + duty) - Equipment costs (rental or owned-depreciation) - Subcontractor costs (audited) - + Allocated indirect costs (% of direct) - + Profit margin per contract ### 2. Modified Total Cost Method - Tendered cost - costs included in scope = baseline - Actual cost - baseline = claim quantum - Subject to challenge if Contractor's tender was below cost ### 3. Measured Mile Method (Productivity Loss) - Compare productivity in "unimpacted period" vs "impacted period" - Calculate cost differential per unit of work - Most credible method; demands rigorous time records ### 4. Time-Impact Analysis (Delay Claims) - Window analysis or As-Planned-vs-As-Built - Critical Path Method (CPM) schedule - Identify pacing delays vs concurrent delays - Use accepted P6/MS Project schedules; recommend Hatcheted Sweep methodology ## Disruption vs Delay - **Delay** — extends end date of activity / project - **Disruption** — same end date but higher cost / lower productivity - Often confused in pleadings; courts distinguish strictly - Pakistan practice: Document disruption with daily production reports + lookup tables ## Defending Against Contractor Claims (Employer's Tactics) 1. **Pre-emptive variation discipline** — refuse to instruct unless variation order issued (preserves quantum at "instructed scope" level) 2. **Insist on time-bar compliance** — accept no claim past 28 days; record letter back 3. **Demand Modified Total Cost backup, not Total Cost** — Total Cost is suspect 4. **Counter-claim for delay damages (LDs)** — set off against Contractor claims 5. **DAAB engagement early** — Pakistan refineries have used Standing DAAB to discipline claim creep 6. **Cap exposure via Sub-Clause 17.6 (cap of liability typically 100% CP)** — make sure not waived ## Common Mistakes (Both Sides) | Side | Mistake | Consequence | |---|---|---| | Contractor | Missing 28-day notice | Time-bar — claim lost | | Contractor | Mixing change order with claim | Distinction critical; not interchangeable | | Contractor | Inadequate concurrent delay analysis | Tribunal apportions delay between parties | | Employer | Constructive variations not documented | Contractor's claim accepted | | Employer | Slow Engineer's determinations | Contractor accelerates DAAB referral | | Employer | Set-off of liquidated damages without basis | Tribunal restores set-off and adds interest | ## Pakistan Specific - **Limitation Act 1908** — 3-year limitation period for contract claims - **Pakistani arbitration**: Arbitration Act 2017 (recent reform); enforces UNCITRAL awards; LCIA seat preferred for international - **Karachi seat arbitration**: Increasingly common; commercial courts established at Karachi/Lahore - **Sovereign protection**: When State or Government instrumentalities party, immunity issues; foreign-seat arbitration preferred