# FIDIC 2017 Suite — Sub-Clause Map for Refining/Petrochem EPC ## The Three Rainbow Books (2017 Edition) | Book | Color | Use Case | Risk Allocation | Pakistan Use | |---|---|---|---|---| | **Red Book** (Construction) | Red | Employer-designed, contractor-built (BoQ measurement) | Employer takes design risk | OGRA pipelines, downstream incremental works | | **Yellow Book** (Plant & Design-Build) | Yellow | Contractor designs to Employer's Requirements | Contractor takes design + execution risk | Refinery upgrades, process plant additions | | **Silver Book** (EPC/Turnkey) | Silver | Single-point lump sum turnkey | Contractor takes virtually all risk | Greenfield refinery/petrochem, hydrogen, off-site/utilities packages | ## Critical Sub-Clauses (2017 Numbering) ### Notice Discipline — The 28-Day Clock | Sub-Clause | Topic | Time Bar | Consequence of Missing | |---|---|---|---| | **20.2.1** | Notice of Claim (Contractor) | 28 days after event known | **Time-barred** — claim invalid | | **20.2.2** | Fully detailed claim | 84 days after notice | Claim limited to material in submission | | **20.2.4** | DAAB decision | 84 days after referral | Notice of Dissatisfaction within 28 days else final | | **20.2.5** | Amicable settlement | 56 days post-NoD | Then arbitration | | **3.7** | Engineer's determination | Reasonable time | Subject to DAAB if disputed | | **8.4** | EOT submission | 28 days from event | Same time-bar logic | ### Variation Procedure | Sub-Clause | Mechanism | |---|---| | **13.1** | Employer's right to vary scope | | **13.2** | Value engineering proposals by Contractor (50/50 share of savings typical) | | **13.3.1** | Variation by Instruction (Employer initiates) | | **13.3.2** | Variation by Request for Proposal (Contractor priced) | | **13.5** | Provisional Sums | | **13.8** | Adjustments for changes in cost (price escalation formula) | ### Force Majeure / Exceptional Events (2017 nomenclature) | Sub-Clause | Topic | |---|---| | **18.1** | Definition of Exceptional Event | | **18.2** | Notice of Exceptional Event (14 days) | | **18.3** | Duty to minimize delay | | **18.4** | Consequences (relief on time, sometimes cost) | | **18.5** | Optional termination after 84 days continuous | | **18.6** | Release from performance | ### Termination Clauses | Sub-Clause | Initiator | Trigger | |---|---|---| | **15.1** | Employer | Notice to correct breach | | **15.2** | Employer | Termination for default (Contractor) | | **15.5** | Employer | Termination for convenience | | **16.1** | Contractor | Suspension for non-payment | | **16.2** | Contractor | Termination for Employer default | | **18.5** | Either | Prolonged exceptional event | | **19.2** | Insurance & risk allocation (re-numbered in 2017) | ### Dispute Avoidance / Adjudication Board (DAAB) — NEW in 2017 - **Mandatory standing board** of 1 or 3 members (vs ad-hoc DAB in 1999) - Constituted within 28 days of contract effectiveness - Members visit site quarterly for "Dispute Avoidance" meetings - Decisions binding pending final arbitration; "Notice of Dissatisfaction" required within 28 days to preserve arbitration right ### Insurance Allocation (Silver Book typical) | Cover | Who Procures | Coverage | |---|---|---| | CAR (Construction All Risks) | Contractor | Material damage during construction | | MAS (Marine Cargo) | Contractor or Employer | Imported plant in transit | | EAR (Erection All Risks) | Contractor | Erection phase of plant | | TPL (Third Party Liability) | Contractor | Off-site claims | | Employer's Liability | Contractor | Workers' injury | | Professional Indemnity | Contractor + Designer | Design errors | | Delay in Start-Up (DSU) | Employer | Loss of revenue from late COD — Yellow/Silver Book Annex | ## Silver Book vs Yellow Book — Risk Decision Matrix **Silver Book preferred when:** - Lender financeability demands turnkey delivery - Owner has limited technical staff for ongoing oversight - Site conditions are well-characterized - Process licensor terms permit single-package delivery **Yellow Book preferred when:** - Process license terms require Employer mediation - Site conditions uncertain (subsurface, brownfield interfaces) - Multiple contracts will interface (utilities, offsites, process) - Employer wants design review milestones **Critical Silver Book risk premium**: 8-15% on contract price for risk transfer; **don't accept Silver if total value