# Checking the promised date against the shop **Quoting a date the shop cannot hit is how a plant loses a customer twice** — once when the job is late, and again when they remember it during the next RFQ. A price that is right and a date that is wrong is a bad quote. The date is frequently the thing the customer actually cares about. --- ## What the check does Read the planning or schedule export and answer one question: **given what is already committed, can this job be delivered by the requested date?** Work through, in order: 1. **The work content this job adds** — setup plus run hours by work centre, from each operation's winning rung on the ladder (`hours-ladder.md`), with that basis named: *"Cell B: 31.4 h, rung 2, closed-job actuals"*. A load check built on first-principles hours says so. Work centres come from the routing, or from the machine class to work centre map in the Plant context for a geometry-derived operation. 2. **What is already loaded** on those work centres between now and the requested date. 3. **Material lead time**, which frequently dominates. A four-week steel lead time makes a three-week delivery impossible regardless of what the machines are doing. 4. **Outside processing lead time**, which is easy to forget and often the real constraint — black oxide at five working days a lot is a week the machines cannot recover. 5. **Whether the requested date survives all four.** --- ## What to report **If the date can be met**, say so and say what it depends on — usually material arriving and the current load holding. **If it cannot, say so, and give the earliest date that can.** A quote that silently promises an impossible date is the failure this step exists to prevent; one that offers a realistic alternative is a commercial conversation the estimator can actually have. > *"The requested 3 November is not achievable. Cell B is loaded to 92% through > late October on committed work, and the 6061-T6 is on a four-week lead time > against an order that has not been placed. The earliest defensible date is 21 > November, assuming material is ordered this week. If 3 November is firm, the > conversation is about what gets displaced — worth flagging to scheduling > before this goes out."* **Name what was checked and what was not.** A load check that looked at machine hours but could not see labour availability should say so. That is the difference between a caveat the estimator can weigh and a promise they cannot. --- ## This is not finite-capacity scheduling The same boundary `daily-production-report` holds for reschedule proposals applies here, for the same reason. **Producing an optimal shop schedule is a constraint-optimisation problem, and a language model asked to do it will return a plausible-looking answer that quietly violates constraints** — which is worse than returning nothing, because it looks authoritative. What is in scope is a **load check with its reasoning shown**: here is the work this adds, here is what is already committed on those work centres, here is where it does not fit. Not a re-optimised shop calendar. --- ## Degradation — and it must not be silent **Without a planning or schedule export**, the quote carries a stated lead time with an explicit caveat: > *"Lead time quoted at 8 weeks from receipt of order, based on the routing and > normal material lead time. **This has not been checked against current shop > load** — no schedule export was available. Confirm with scheduling before > release."* **Never a silent omission.** A quote with no date caveat reads as a date that was checked, and that is precisely the wrong impression to leave with an estimator about to commit to a customer. Where the export exists but is stale, state the load **as of** its last refresh rather than as current. A load picture from three weeks ago has missed everything booked since, and per `../../../shared/absent-is-not-zero.md` a stale figure presented as current is the worst available outcome.