{ "id": "c7890def-1234-5678-abcd-ef0123456789", "containerId": "b5623fe1-4e59-4d33-a928-f1234abc5678", "displayId": 142, "title": "Rebar spacing does not match structural drawings", "description": "Rebar spacing in the east abutment footing is 18 inches OC, but structural drawings specify 12 inches OC. Requires corrective action before concrete pour scheduled for next week.", "status": "open", "issueTypeId": "type-quality-001", "issueSubtypeId": "subtype-structural-001", "dueDate": "2026-04-25", "startDate": "2026-04-19", "locationId": "loc-east-abutment-001", "locationDescription": "East Abutment Footing - Grid Line E5", "assignedToId": "user-engineer-jsmith-001", "assignedToType": "user", "createdBy": "user-inspector-bdoe-002", "createdAt": "2026-04-19T08:15:00Z", "updatedAt": "2026-04-19T08:15:00Z", "closedBy": null, "closedAt": null, "commentCount": 2, "attachmentCount": 3, "linkedDocuments": [ { "urn": "urn:adsk.wipprod:fs.file:vf.abc123def456" } ] }