--- name: eurosys-workflow description: Use when planning a EuroSys campaign end to end — choosing between the spring and fall gates of an edition, backward-scheduling system building and evaluation from the abstract deadline, handling the notification-to-revision-to-resubmission pipeline, and landing camera-ready, artifacts, and April travel for the conference. --- # EuroSys Workflow Use this as the project plan around a EuroSys submission. The venue's calendar is its most distinctive constraint: one April conference fed by two submission gates roughly four months apart. Dates below are the EuroSys 2027 cycle as rendered on 2026-07-08 (`2027.eurosys.org/cfp.html`); re-pull the live CFP before committing the team to any of them. ## The 2027 board | Milestone | Date | Status on 2026-07-08 | |---|---|---| | Spring abstracts / papers | May 7 / May 14, 2026 | Closed | | Spring notification | August 21, 2026 | ~6 weeks away | | Fall abstracts / papers | September 17 / 24, 2026 | ~10 / 11 weeks away | | Fall notification | January 29, 2027 | — | | Camera-ready (both cohorts) | ~March 5, 2027 (third-party, 待核实) | — | | Conference, Rabat, Morocco | April 19–23/24, 2027 (end date 待核实) | — | So a team starting today has one live target: the fall gate. A team with a spring submission under review is in the quiet zone — the right use of that zone is artifact preparation and boundary experiments, both of which pay off regardless of the August outcome. ## Backward plan to the fall paper gate (Sep 24, 2026) ```text T-10w now System feature-frozen for the paper's claims; eval matrix written T-8w late Jul Decomposition + cost experiments running nightly; plots automated T-6w mid Aug Full draft exists in acmart[sigplan] review mode; internal read #1 T-4w late Aug Boundary/worst-case runs done; related-work sweep incl. dblp pass T-3w early Sep External mock review by a systems colleague outside the project T-2w Sep 10 Claims-to-evidence audit; every number has provenance T-1w Sep 17 ABSTRACT GATE — title/abstract/authors/topics/conflicts final T-0 Sep 24 Paper gate — identity sweep on the final PDF, upload with margin ``` The two-gate structure is a gift: the abstract week is for polishing, and the title and abstract registered at T-1w determine which reviewers bid — write them for bidding, not as placeholders. ## Branching after notification - **Accept** → camera-ready lane (ACM forms, final build) plus the sysartifacts artifact lane in parallel; they contend for the same people, so name owners. - **One-shot revision** → the condition list becomes the plan of record; the resubmission target is the next round's gate. Feasibility call within one week (see `eurosys-author-response`). - **Reject** → the same round next edition is the earliest legal EuroSys return. Decide between a genuine year of strengthening or retargeting a sibling venue whose next deadline fits the work's maturity (`eurosys-topic-selection` has the routing table). ## Standing risks and their owners | Risk | Early symptom | Owner | |---|---|---| | Eval starts too late | No automated plots by T-8w | Experiments lead | | Baseline dispute | Tuning provenance undocumented | Whoever runs baselines | | Anonymity leak | Repo/PDF never swept | Submission owner | | Revision-condition overrun | No feasibility call in week one | Project lead | | Travel/visa for Rabat | Unchecked entry requirements post-accept | Presenting author | ## Using the quiet zones The two-gate calendar creates long author-side silences (submission to notification is ~14 weeks). Teams that treat them as vacations pay later: - **Artifact runway:** build the claims map and environment contract now; AE and camera-ready will collide with each other after notification. - **Boundary experiments:** the worst-case runs cut on deadline week are exactly what a revision condition list will demand — run them anyway. - **Preprint and talk policy:** decide, against the round's anonymity wording (待核实), what can be presented publicly while under review. - **Next-gate insurance:** keep the evaluation harness runnable; if the outcome is a revision, the conditions arrive with a four-month fuse. ## Coordination notes for multi-author teams - One person owns the HotCRP record (fields, conflicts, uploads); shared ownership of forms produces last-minute permission surprises. - The evaluation lead and the writing lead exchange the claims-to-evidence map weekly from T-6w; prose drifting ahead of data is how overclaiming enters a draft innocently. - Book the mock reviewer at T-4w for a T-3w read; systems colleagues who can simulate a EuroSys review are scarce in September. ## Two-gate portfolio thinking Groups with multiple projects should stagger them across the two gates rather than crowding the fall: a spring submission gets its decision in August with time to revise into the fall, while a fall submission's revision path crosses into the *next* edition. Maturity at gate time — not preference for a season — should pick the gate. ## Output format ```text [Live target] [Stage now] building / evaluating / drafting / submitted / revising / accepted [Backward-plan health] [Post-notification branch] [Owners] named person> ```