--- name: mobicom-workflow description: Use when planning a MobiCom campaign across the rolling two-deadlines-per-year calendar — deciding which round to target and which edition it feeds, building a backward schedule that leaves room for over-the-air experiments, and sequencing the two-round review, rebuttal, and one-shot revision so a slip does not silently cost an edition. --- # MobiCom Workflow MobiCom's calendar is the part authors from single-deadline venues mis-plan most. There are **two rounds a year**, each feeds a **different edition**, and inside each round the review runs in **two stages with a rebuttal**. Plan the campaign around those facts, not around a single "the deadline." ## Which round, which edition Before scheduling anything, pin two facts on the live CFP / HotCRP `/deadlines` page: - **Which edition does this round feed?** The summer/fall round opening after MobiCom 2026 competes for **MobiCom 2027**. Submitting to it is a bet on next year's program, not this year's. - **What is the AoE cutoff in local time?** MobiCom prints an Eastern clock time for an AoE deadline; convert once, for every coauthor (`mobicom-submission`). Picking the round is a research-readiness decision: the earlier round gets your work in front of reviewers sooner, but only if the over-the-air evaluation is actually done. ## Backward schedule from the paper cutoff Radio experiments do not compress the way a proof or an ablation does — testbeds break, channels drift, and volunteers for mobility runs have to be scheduled. Work backward: | Weeks before paper cutoff | Milestone | |---|---| | T-12 | Fit and round locked (`mobicom-topic-selection`); testbed reserved; IRB/site access if human mobility | | T-8 | Core mechanism frozen; headline over-the-air experiment running, not just designed | | T-5 | Baselines on tuned hardware; energy and channel measurement complete (`mobicom-experiments`) | | T-3 | Full draft; provenance ledger closed (`mobicom-reproducibility`) | | T-2 | Writing-style and related-work passes; supplementary/appendix split | | T-1 (abstract cutoff) | Abstract registered on HotCRP; author list and conflicts entered | | T-0 (paper cutoff, AoE) | Submission audit and upload (`mobicom-submission`) | The rule of thumb from wireless deadline archaeology: **the mobility and failure-condition experiments are always the ones cut when the schedule slips**, and they are the ones reviewers value most. Protect them by running them before the final scale sweeps. ## Inside the round: two stages plus rebuttal ```text Round opens -> submission Stage 1 review -> either EARLY REJECT (with reviews) or advance Stage 2 review -> reviews released -> REBUTTAL window -> decision Decision space: accept / one-shot revision / reject ``` - An **early reject after stage 1** returns reviews you can use for the *next* round — treat it as data, not just a loss (`mobicom-review-process`). - The **rebuttal** is short and bounded; plan the coauthor time for it now, because it lands on a fixed clock you do not control (`mobicom-author-response`). - A **one-shot revision** is a months-long commitment to a required-changes list, often with the same reviewers — budget the experiments it will demand before accepting the plan. ## Which edition a slip costs Because rounds feed editions, missing the summer round does not just delay a few weeks — it pushes the work to the winter round of the *same* edition or, if that slips too, to the next edition entirely. Map the cost explicitly: - On track for the summer round → decision months earlier. - Slip to the winter round → same edition, later PC meeting. - Slip again → next edition; a full year of program calendar. State which of these the current plan is really on, in machine-days of remaining testbed work, so "we'll make summer" is a claim with arithmetic behind it, not optimism. ## During the long review silence MobiCom reviews take weeks. Do not stall: extend the evaluation you already have (more mobility traces, a deployment week, an energy sweep) so that whatever the letter says — rebuttal, revision, or the next round — you are answering from a stronger position than the submitted version. ## Output format ```text [Round] which round + which edition it feeds + AoE cutoff (local) [Readiness] over-the-air evaluation done? y/n — gating experiments named [Backward schedule] milestones with dates; slip risks flagged [Slip cost] which edition a miss pushes the work to [Post-decision plan] rebuttal / revision / next-round readiness ```