# EOL Process Example — Industrial **Product:** NFA-200 series retrofit controller (Northfield Automation) **Level:** 3 — Heavy · **Elapsed:** ~30 months and still running **Context:** ~120 installations, 8 channel partners, service contracts through 2028, UL 508A and CE certified. NFA-500 is the successor but needs a different mounting bracket — every migration is a scoped site visit. **Why this example exists:** the SaaS example runs the six phases in order. This one shows the loop — **Phase 2 sent the process back to Phase 1, and the outcome changed** from "retire the NFA-200" to "stop selling it, keep servicing it, and fund the retrofit path first." That backwards step is the process working. --- ```markdown ## EOL Process Tracker: NFA-200 Series Retrofit Controller **Level**: 3 -- Heavy **Landing place**: Replacement (NFA-500) -- NOT READY: no drop-in retrofit path **Current phase**: 6 (in progress -- service obligations run to Dec 2028) **Target announcement date**: March 31, 2026 **Target EOL date**: Not scheduled --- ### Phase 1: Decide (first pass) Status: [x] Superseded (Oct 2025) - Trigger: Internal only. Manufacturing wanted the NFA-200 line reallocated - Verdict (first pass): Go -- retire the NFA-200, migrate the base to NFA-500 - Obligations to check: service agreements, UL/CE certification, spare parts, 8 channel partner agreements **DP1**: Go, and is the landing place real? - [x] Verdict is Go - [ ] Landing place readiness -- ASSUMED ready, not verified - Note: this assumption is what Phase 2 broke --- ### Phase 2: Align Status: [x] Done (Nov 2025 - Feb 2026) | # | Stop | Held? | What it surfaced | |---|---|---|---| | 1 | Legal (contracts) | [x] | Service agreements run to Dec 2028. Not terminable | | 2 | Regulatory | [x] | Certification unaffected, but 14 sites run validated processes | | 3 | Finance | [x] | Service revenue through 2028 is material. Spares carry cost modest | | 4 | Operations / Supply Chain | [x] | Spares coverage to 2028 feasible with one final buy | | 5 | Executives | [x] | See DP2 -- the ask changed here | | 6 | Sales | [x] | Three customers mid-standardization on NFA-200 across sites | | 7 | Channel partners (8) | [x] | Two partners holding stock; one mid-bid on a project | | 8 | Service org | [x] | Can staff to 2028; two techs retire in 2027 | | 9 | Key accounts (3) | [x] | Retrofit needs a production shutdown at 2 of 3 sites | | 10 | Engineering | [x] | Retrofit bracket designable, ~9 months, unfunded | | 11 | Marketing | [x] | Held pending decision | **DP2**: Did anything invalidate the decision? - [ ] No blocking contract, regulation, or commitment <-- FAILED - [ ] Landing place still holds <-- FAILED - **Returned to Phase 1.** Two findings broke the original verdict: 1. Service agreements to Dec 2028 cannot be terminated (obligation lock) 2. NFA-500 is not a drop-in -- 120 site visits, 2 of 3 sampled sites need a production shutdown, and the bracket work is unfunded (no landing place) --- ### Phase 1: Decide (second pass) Status: [x] Done (Feb 2026) - Trigger restated honestly: manufacturing capacity, not customer need - Verdict: **Hold on EOL. Go on End of Sale.** - Reasoning: EOS returns the manufacturing line -- which was the actual ask -- without committing to a shutdown date we cannot keep - Condition: fund the retrofit bracket work as the precondition to ever scheduling an EOL - Precondition to schedule EOL: validated retrofit path with per-site cost, plus installed base below 20 units **DP1 (second pass)**: Go, and is the landing place real? - [x] Verdict is Go-with-conditions, scoped to End of Sale only - [x] Landing place honestly recorded as NOT READY - [x] Phase 5 permitted for an EOS announcement; an EOL announcement is blocked --- ### Phase 3: Plan Status: [x] Done (Mar 2026) - Gates in scope: NSC, EOS, EOE, EOR, EOM, EOSRV - Gates deliberately excluded: EOL -- not scheduled; precondition recorded - EOR included because service agreements run past EOS (contract-driven) - Enablement complete by: March 13, 2026 (partners March 6) - Announcement date: March 31, 2026 **DP3**: Every item owned, every date real? - [x] No unowned items - [x] No invented dates -- EOL carries "Not scheduled" plus its precondition - [x] Data (telemetry retention), contracts (per-account end dates), access (n/a), money (service wind-down model) all covered - [x] Phase 6 review on the checklist -- Owner: Product - [x] Post-EOL item added: reassess the EOL precondition -- Owner: Product --- ### Phase 4: Prepare Status: [x] Done (Mar 2026) - Materials built: Support/field FAQ, sales talking points, objection handling, escalation playbook, channel partner brief, 90-minute training with role-play - Escalation owners: L1 Field service desk, L2 Ravi, L3 Elena, Exec Tom - Partners briefed: March 6, 2026 -- 25 days before public notice **DP4**: Enablement complete? - [x] Field techs could answer "when does my controller stop working?" correctly ("it doesn't") without hedging - [x] Role-played the bricking, mounting, and audit objections - [x] Offers pre-approved; two explicitly forbidden (no parts past 2028, no NFA-500 drop-in claims) - [x] Partners had the brief and forbidden-claims list before customers --- ### Phase 5: Announce Status: [x] Done (March 31, 2026) - Size: Full - Path: Replacement, with channel and regulatory obligations - Segments: customer notice, partner pack, validated-process customers received the change-control documentation package - Comms calendar: Mar 31 status change, Sep 2026 last-time-buy reminder, Jan 2027 final order window, Dec 2027 non-renewal notices **DP5**: Does it survive contact? - [x] Legal reviewed service, refund, and certification language - [x] Consistent with Phase 2 -- the three mid-standardization accounts were called before the notice and given reserved last-time-buy quantities - [x] Field service and partners had it first - [x] Passes the sticky-note test: "your units are unaffected; last order March 31, 2027" --- ### Phase 6: Close Status: [ ] In progress (through Dec 2028) - Gates closed: NSC Mar 2026, EOS Mar 2027, EOE Mar 2027 -- signed off - Gates pending: EOR Dec 2027, EOM Dec 2028, EOSRV Dec 2028 - Transition progress: 31 of 120 sites retrofitted to NFA-500 - Retention vs. forecast: 100% of service agreements retained to date **Closure items** - [x] Manufacturing line reallocated (the original ask) -- April 2027 - [x] Interim lessons-learned review written after EOS -- Owner: Product - [ ] Telemetry export and archive (due Dec 2028) - [ ] Contracts settled; non-renewals confirmed in writing (in progress) - [ ] Revenue recognition closed (due Dec 2028) - [ ] **Reassess the EOL precondition** -- Owner: Product, review each Q4 **DP6**: Is this actually closed? - [ ] Not yet -- service obligations run to December 2028 --- ### Interim lessons learned (excerpt, written after EOS) - The first-pass Phase 1 verdict was wrong because we assumed the landing place was ready without checking. One question -- "is the NFA-500 a drop-in for the installed base?" -- would have caught it in October instead of February. - Going back to Phase 1 cost four months and saved us from announcing a shutdown date for 120 controllers we had no way to migrate. - Executives asked for an EOL and accepted an EOS because we arrived at Stop 5 with four conversations' worth of evidence. Sequencing them fifth, not first, is what made that possible. - Briefing partners 25 days early cost nothing and surfaced a partner mid-bid on an NFA-200 project we would have torpedoed. ### Assumptions to Validate - Assumes no service agreement extends past December 2028 (Legal confirmed) - Assumes component supply supported the final build (held) - Assumes retrofit bracket funding stays approved (at risk -- re-check each Q4) ``` --- ## What to notice - **Phase 1 appears twice, and the first pass is marked Superseded rather than deleted.** The record of the wrong verdict — and specifically the unchecked box next to "landing place readiness" — is the most instructive line in the tracker. - **DP2 is the gate that earned its keep.** Both of its checks failed, and the process looped. Four months looked like a delay and was actually the avoidance of announcing a shutdown date for 120 controllers with no migration path. - **The verdict got cheaper, not smaller.** EOS returned the manufacturing line, which was the actual internal ask, without committing to an EOL nobody could deliver. Separating the presenting problem from the underlying one is what Phase 1 is for. - **Phase 6 is legitimately open for two more years.** Closure is the obligation end date, not the announcement. Note the interim review written after EOS — waiting until 2028 to capture lessons would have lost them. - **A deferred decision has a named owner and a recurring review.** "Reassess the EOL precondition — Owner: Product, review each Q4." Without that line, "not scheduled" quietly becomes "forgotten," and the next PM inherits a product with no plan and no explanation.