# EOL Process Example — SaaS **Product:** Fieldlight Classic Dispatch **Level:** 2 — Standard · **Elapsed:** ~12 months, decision to closure **Context:** ~800 accounts, $2.4M ARR, annual contracts, sold direct. Replaced by Fieldlight Next Scheduling. ~30 accounts use custom dispatch rules that don't carry over. This example runs all six phases in order — the clean case. The industrial example shows what happens when Phase 2 sends you backwards. --- ```markdown ## EOL Process Tracker: Fieldlight Classic Dispatch **Level**: 2 -- Standard **Landing place**: Replacement (Fieldlight Next) -- Gap: custom dispatch rules **Current phase**: 6 (complete) **Target announcement date**: March 1, 2026 **Target EOL date**: December 31, 2026 --- ### Phase 1: Decide Status: [x] Done (Nov 2025) - Trigger: Support cost. Classic drove ~40% of support volume on ~15% of revenue - Verdict: Go-with-conditions - Condition: the ~30 custom-rule accounts need a named plan before announcement - Obligations to check: 800 annual contracts, renewal date language, platform SLA scope **DP1**: Go, and is the landing place real? - [x] Verdict is Go-with-conditions - [x] Landing place named: Fieldlight Next, at parity except custom rules - [x] Landing place gap noted -- Phase 5 gated on the custom-rule plan --- ### Phase 2: Align Status: [x] Done (Dec 2025 - Jan 2026) | # | Stop | Held? | What it surfaced | |---|---|---|---| | 1 | Legal | [x] | No Classic-specific terms. SLA is platform-wide. Date cleared | | 2 | Finance | [x] | Classic ARR is $2.4M. Retention target set at 90% | | 3 | Sales | [x] | Two accounts told "Classic supported indefinitely" -- unwind needed | | 4 | Marketing | [x] | Q1 webinar featured Classic. Pulled | | 5 | CS | [x] | 6 of the 30 custom-rule accounts already at renewal risk | | 6 | Difficult customers (3) | [x] | Two undocumented v1 API integrations found | | 7 | Engineering | [x] | Internal billing job reads Classic dispatch data | | 8 | Support | [x] | Needs 2 temp headcount for the March-June window | **DP2**: Did anything invalidate the decision? - [x] No blocking contract, regulation, or commitment - [x] Landing place still holds -- gap is real but bounded and funded - [x] Two field commitments logged for individual handling - Decision unchanged. Date held. --- ### Phase 3: Plan Status: [x] Done (Jan 2026) - Gates in scope: NSC, EOS, EOE, EOM, EOL - Gates deliberately excluded: EOR (annual contracts expire naturally); EOSRV (SaaS -- no post-EOL service obligations) - Enablement complete by: February 20, 2026 <-- precedes announcement - Announcement date: March 1, 2026 **DP3**: Every item owned, every date real? - [x] No unowned items - [x] All dates defensible; none invented - [x] Data (90-day export window), contracts (Legal cleared), access (v1 API consumers inventoried), money (Q4 reforecast) all covered - [x] Phase 6 review on the checklist -- Owner: Product --- ### Phase 4: Prepare Status: [x] Done (Feb 2026) - Materials built: Support FAQ, sales talking points, objection handling, escalation playbook - Escalation owners: L1 Support team, L2 Priya, L3 Marcus, Exec Dana - Partners briefed: n/a (sold direct) **DP4**: Enablement complete? - [x] Reps could name the escalation owner unprompted - [x] Role-played the "we just renewed" and "no custom rules" objections - [x] Offers pre-approved: priority slots, 1-on-1 rebuilds, exec call over $25K ARR - [x] Support had the pack Feb 20, nine days before announcement --- ### Phase 5: Announce Status: [x] Done (March 1, 2026) - Size: Standard - Path: Replacement - Segments: all-accounts email; separate note to the 30 custom-rule accounts sent 48 hours earlier by their CSMs - Comms calendar: Mar 1 announcement, May 15 EOE reminder, Sep 1 EOM reminder, Nov 15 final export notice, Dec 15 last call **DP5**: Does it survive contact? - [x] Legal reviewed the contract and refund language - [x] Consistent with Phase 2 findings -- the two "indefinite support" accounts were called individually before the blast - [x] Support had it first - [x] Passes the sticky-note test: migrate at fieldlight.com/next-migration before December 31 --- ### Phase 6: Close Status: [x] Done (March 2027) - Gates closed: EOS Mar 1, EOE Jun 1, EOM Oct 1, EOL Dec 31 -- all signed off - Transition final: 781 of 800 accounts migrated - Retention vs. forecast: 94% ARR retained against a 90% target **Closure items** - [x] Exports available through March 31, 2027; deletion scheduled April 2027 - [x] Contracts settled; no disputes - [x] Revenue recognition closed December 31 - [x] Classic infrastructure decommissioned January 2027 - [x] Lessons-learned review written -- Owner: Product - [x] No deferred decisions **DP6**: Is this actually closed? - [x] Data settled, contracts closed, money recognized, review written --- ### Lessons learned (excerpt) - The difficult-customer stop paid for the whole process. Two undocumented v1 API integrations would have broken at EOE and generated a public incident. - We under-invested in Phase 4 sales enablement. Sales asked for the comparison table twice before we produced one with the gaps included; the first version had no gaps and they stopped trusting it. - 19 accounts never migrated and churned. 11 of them were in the custom-rule segment. The 1-on-1 rebuild offer went out too late -- it should have been in the March 1 announcement, not the May reminder. - Next time: start the custom-segment outreach before the general announcement, not 48 hours before. ### Assumptions to Validate (from Phase 1, resolved) - Support volume estimate of 40% -- measured at 37%, close enough - Custom-rule account count of ~30 -- actual was 34 ``` --- ## What to notice - **DP2 cleared explicitly rather than silently.** The tracker records "Decision unchanged. Date held." Even when nothing blocks, saying so is what makes the gate real rather than decorative. - **The gap survived all the way to the outcome.** Custom dispatch rules appear in Phase 1 as a condition, Phase 2 as a risk (6 of 30 at renewal risk), Phase 4 as an objection with a pre-approved offer, Phase 5 as a segmented send — and in Phase 6 as 11 of the 19 churned accounts. The thing most likely to hurt you should be traceable through every phase. - **Retention is the reported outcome, not completion.** 94% against a 90% target. Checklist completion would have read as 100% and taught nobody anything. - **The lessons-learned review is critical of the process that produced it.** Naming the late 1-on-1 offer as the cause of 11 churned accounts is the entire value of Phase 6. A review that concludes "went well" is a review that didn't happen.