[ { "site_id": "S001", "site_name": "Downtown Plaza", "estimated_materials_cost": 45000, "actual_materials_cost": 47500, "estimated_labor_cost": 32000, "actual_labor_cost": 34500, "estimated_duration_days": 90, "actual_duration_days": 95 }, { "site_id": "S002", "site_name": "Harbor View Complex", "estimated_materials_cost": 78000, "actual_materials_cost": 82000, "estimated_labor_cost": 56000, "actual_labor_cost": 59000, "estimated_duration_days": 120, "actual_duration_days": 125 }, { "site_id": "S003", "site_name": "Westside Mall", "estimated_materials_cost": 120000, "actual_materials_cost": 115000, "estimated_labor_cost": 85000, "actual_labor_cost": 82000, "estimated_duration_days": 150, "actual_duration_days": 145 }, { "site_id": "S004", "site_name": "Riverside Tower", "estimated_materials_cost": 95000, "actual_materials_cost": 102000, "estimated_labor_cost": 68000, "actual_labor_cost": 73000, "estimated_duration_days": 110, "actual_duration_days": 118 }, { "site_id": "S005", "site_name": "Central Park Building", "estimated_materials_cost": 62000, "actual_materials_cost": 64500, "estimated_labor_cost": 44000, "actual_labor_cost": 46000, "estimated_duration_days": 100, "actual_duration_days": 105 }, { "site_id": "S006", "site_name": "Northgate Office", "estimated_materials_cost": 88000, "actual_materials_cost": 95000, "estimated_labor_cost": 63000, "actual_labor_cost": 68000, "estimated_duration_days": 130, "actual_duration_days": 140 }, { "site_id": "S007", "site_name": "Southpoint Retail", "estimated_materials_cost": 54000, "actual_materials_cost": 56000, "estimated_labor_cost": 38000, "actual_labor_cost": 40000, "estimated_duration_days": 85, "actual_duration_days": 88 }, { "site_id": "S008", "site_name": "Eastside Warehouse", "estimated_materials_cost": 71000, "actual_materials_cost": 74000, "estimated_labor_cost": 51000, "actual_labor_cost": 53500, "estimated_duration_days": 95, "actual_duration_days": 98 }, { "site_id": "S009", "site_name": "Hilltop Residence", "estimated_materials_cost": 43000, "actual_materials_cost": 45000, "estimated_labor_cost": 31000, "actual_labor_cost": 32500, "estimated_duration_days": 80, "actual_duration_days": 85 }, { "site_id": "S010", "site_name": "Lakefront Villa", "estimated_materials_cost": 67000, "actual_materials_cost": 72000, "estimated_labor_cost": 48000, "actual_labor_cost": 52000, "estimated_duration_days": 105, "actual_duration_days": 112 }, { "site_id": "S011", "site_name": "Mountain View Estate", "estimated_materials_cost": 91000, "actual_materials_cost": 88000, "estimated_labor_cost": 65000, "actual_labor_cost": 62000, "estimated_duration_days": 125, "actual_duration_days": 120 }, { "site_id": "S012", "site_name": "Sunset Boulevard", "estimated_materials_cost": 58000, "actual_materials_cost": 61000, "estimated_labor_cost": 41000, "actual_labor_cost": 43500, "estimated_duration_days": 92, "actual_duration_days": 97 }, { "site_id": "S013", "site_name": "Ocean Drive Complex", "estimated_materials_cost": 105000, "actual_materials_cost": 112000, "estimated_labor_cost": 75000, "actual_labor_cost": 81000, "estimated_duration_days": 140, "actual_duration_days": 150 }, { "site_id": "S014", "site_name": "Valley Creek Center", "estimated_materials_cost": 76000, "actual_materials_cost": 79000, "estimated_labor_cost": 54000, "actual_labor_cost": 57000, "estimated_duration_days": 108, "actual_duration_days": 113 }, { "site_id": "S015", "site_name": "Pine Ridge Office", "estimated_materials_cost": 49000, "actual_materials_cost": 51500, "estimated_labor_cost": 35000, "actual_labor_cost": 37000, "estimated_duration_days": 87, "actual_duration_days": 90 }, { "site_id": "S016", "site_name": "Maple Street Building", "estimated_materials_cost": 83000, "actual_materials_cost": 87000, "estimated_labor_cost": 59000, "actual_labor_cost": 62500, "estimated_duration_days": 115, "actual_duration_days": 120 }, { "site_id": "S017", "site_name": "Oak Lane Plaza", "estimated_materials_cost": 64000, "actual_materials_cost": 66500, "estimated_labor_cost": 46000, "actual_labor_cost": 48000, "estimated_duration_days": 98, "actual_duration_days": 102 }, { "site_id": "S018", "site_name": "Cedar Point Tower", "estimated_materials_cost": 97000, "actual_materials_cost": 103000, "estimated_labor_cost": 69000, "actual_labor_cost": 74000, "estimated_duration_days": 128, "actual_duration_days": 135 }, { "site_id": "S019", "site_name": "Birch Grove Mall", "estimated_materials_cost": 72000, "actual_materials_cost": 75000, "estimated_labor_cost": 52000, "actual_labor_cost": 54500, "estimated_duration_days": 102, "actual_duration_days": 107 }, { "site_id": "S020", "site_name": "Willow Park Complex", "estimated_materials_cost": 55000, "actual_materials_cost": 57500, "estimated_labor_cost": 39000, "actual_labor_cost": 41000, "estimated_duration_days": 89, "actual_duration_days": 93 }, { "site_id": "S021", "site_name": "Elm Avenue Center", "estimated_materials_cost": 86000, "actual_materials_cost": 90000, "estimated_labor_cost": 61000, "actual_labor_cost": 64500, "estimated_duration_days": 118, "actual_duration_days": 125 }, { "site_id": "S022", "site_name": "Spruce Hill Office", "estimated_materials_cost": 61000, "actual_materials_cost": 64000, "estimated_labor_cost": 43000, "actual_labor_cost": 45500, "estimated_duration_days": 94, "actual_duration_days": 99 }, { "site_id": "S023", "site_name": "Aspen Heights Building", "estimated_materials_cost": 99000, "actual_materials_cost": 96000, "estimated_labor_cost": 71000, "actual_labor_cost": 68000, "estimated_duration_days": 132, "actual_duration_days": 128 }, { "site_id": "S024", "site_name": "Redwood Valley Plaza", "estimated_materials_cost": 68000, "actual_materials_cost": 71000, "estimated_labor_cost": 49000, "actual_labor_cost": 51500, "estimated_duration_days": 100, "actual_duration_days": 105 }, { "site_id": "S025", "site_name": "Cypress Bay Tower", "estimated_materials_cost": 81000, "actual_materials_cost": 85000, "estimated_labor_cost": 58000, "actual_labor_cost": 61000, "estimated_duration_days": 112, "actual_duration_days": 118 }, { "site_id": "S026", "site_name": "Juniper Creek Mall", "estimated_materials_cost": 57000, "actual_materials_cost": 59500, "estimated_labor_cost": 40000, "actual_labor_cost": 42000, "estimated_duration_days": 90, "actual_duration_days": 94 }, { "site_id": "S027", "site_name": "Sequoia Ridge Complex", "estimated_materials_cost": 93000, "actual_materials_cost": 98000, "estimated_labor_cost": 66000, "actual_labor_cost": 70000, "estimated_duration_days": 122, "actual_duration_days": 130 }, { "site_id": "S028", "site_name": "Magnolia Street Center", "estimated_materials_cost": 66000, "actual_materials_cost": 69000, "estimated_labor_cost": 47000, "actual_labor_cost": 49500, "estimated_duration_days": 97, "actual_duration_days": 102 }, { "site_id": "S029", "site_name": "Poplar Lane Office", "estimated_materials_cost": 74000, "actual_materials_cost": 77500, "estimated_labor_cost": 53000, "actual_labor_cost": 55500, "estimated_duration_days": 106, "actual_duration_days": 111 }, { "site_id": "S030", "site_name": "Sycamore Point Plaza", "estimated_materials_cost": 52000, "actual_materials_cost": 54500, "estimated_labor_cost": 37000, "actual_labor_cost": 39000, "estimated_duration_days": 86, "actual_duration_days": 90 }, { "site_id": "S031", "site_name": "Chestnut Grove Building", "estimated_materials_cost": 89000, "actual_materials_cost": 93000, "estimated_labor_cost": 63000, "actual_labor_cost": 66500, "estimated_duration_days": 119, "actual_duration_days": 126 }, { "site_id": "S032", "site_name": "Hickory Ridge Tower", "estimated_materials_cost": 63000, "actual_materials_cost": 66000, "estimated_labor_cost": 45000, "actual_labor_cost": 47500, "estimated_duration_days": 96, "actual_duration_days": 101 }, { "site_id": "S033", "site_name": "Walnut Valley Mall", "estimated_materials_cost": 101000, "actual_materials_cost": 107000, "estimated_labor_cost": 72000, "actual_labor_cost": 77000, "estimated_duration_days": 135, "actual_duration_days": 143 }, { "site_id": "S034", "site_name": "Beech Creek Complex", "estimated_materials_cost": 70000, "actual_materials_cost": 73500, "estimated_labor_cost": 50000, "actual_labor_cost": 52500, "estimated_duration_days": 103, "actual_duration_days": 108 }, { "site_id": "S035", "site_name": "Fir Hill Office", "estimated_materials_cost": 48000, "actual_materials_cost": 50500, "estimated_labor_cost": 34000, "actual_labor_cost": 36000, "estimated_duration_days": 84, "actual_duration_days": 88 }, { "site_id": "S036", "site_name": "Cherry Lane Plaza", "estimated_materials_cost": 85000, "actual_materials_cost": 89000, "estimated_labor_cost": 60000, "actual_labor_cost": 63500, "estimated_duration_days": 116, "actual_duration_days": 122 }, { "site_id": "S037", "site_name": "Pecan Street Center", "estimated_materials_cost": 59000, "actual_materials_cost": 62000, "estimated_labor_cost": 42000, "actual_labor_cost": 44000, "estimated_duration_days": 93, "actual_duration_days": 98 }, { "site_id": "S038", "site_name": "Cottonwood Tower", "estimated_materials_cost": 96000, "actual_materials_cost": 100000, "estimated_labor_cost": 68000, "actual_labor_cost": 72000, "estimated_duration_days": 127, "actual_duration_days": 134 }, { "site_id": "S039", "site_name": "Dogwood Bay Building", "estimated_materials_cost": 73000, "actual_materials_cost": 76500, "estimated_labor_cost": 52000, "actual_labor_cost": 54500, "estimated_duration_days": 104, "actual_duration_days": 109 }, { "site_id": "S040", "site_name": "Laurel Point Mall", "estimated_materials_cost": 56000, "actual_materials_cost": 58500, "estimated_labor_cost": 40000, "actual_labor_cost": 42000, "estimated_duration_days": 91, "actual_duration_days": 95 }, { "site_id": "S041", "site_name": "Hemlock Ridge Complex", "estimated_materials_cost": 87000, "actual_materials_cost": 91500, "estimated_labor_cost": 62000, "actual_labor_cost": 65500, "estimated_duration_days": 117, "actual_duration_days": 124 }, { "site_id": "S042", "site_name": "Alder Valley Office", "estimated_materials_cost": 65000, "actual_materials_cost": 68000, "estimated_labor_cost": 46000, "actual_labor_cost": 48500, "estimated_duration_days": 99, "actual_duration_days": 104 }, { "site_id": "S043", "site_name": "Basswood Creek Plaza", "estimated_materials_cost": 98000, "actual_materials_cost": 102000, "estimated_labor_cost": 70000, "actual_labor_cost": 73500, "estimated_duration_days": 129, "actual_duration_days": 136 }, { "site_id": "S044", "site_name": "Ironwood Street Tower", "estimated_materials_cost": 69000, "actual_materials_cost": 72000, "estimated_labor_cost": 49000, "actual_labor_cost": 51500, "estimated_duration_days": 101, "actual_duration_days": 106 }, { "site_id": "S045", "site_name": "Locust Hill Center", "estimated_materials_cost": 80000, "actual_materials_cost": 84000, "estimated_labor_cost": 57000, "actual_labor_cost": 60000, "estimated_duration_days": 113, "actual_duration_days": 119 }, { "site_id": "S046", "site_name": "Mesquite Bay Building", "estimated_materials_cost": 54000, "actual_materials_cost": 56500, "estimated_labor_cost": 38000, "actual_labor_cost": 40000, "estimated_duration_days": 88, "actual_duration_days": 92 }, { "site_id": "S047", "site_name": "Persimmon Ridge Mall", "estimated_materials_cost": 92000, "actual_materials_cost": 96500, "estimated_labor_cost": 65000, "actual_labor_cost": 68500, "estimated_duration_days": 121, "actual_duration_days": 128 }, { "site_id": "S048", "site_name": "Sumac Valley Office", "estimated_materials_cost": 62000, "actual_materials_cost": 65000, "estimated_labor_cost": 44000, "actual_labor_cost": 46500, "estimated_duration_days": 95, "actual_duration_days": 100 }, { "site_id": "S049", "site_name": "Tamarack Point Plaza", "estimated_materials_cost": 77000, "actual_materials_cost": 81000, "estimated_labor_cost": 55000, "actual_labor_cost": 58000, "estimated_duration_days": 109, "actual_duration_days": 115 }, { "site_id": "S050", "site_name": "Yew Creek Complex", "estimated_materials_cost": 51000, "actual_materials_cost": 53500, "estimated_labor_cost": 36000, "actual_labor_cost": 38000, "estimated_duration_days": 85, "actual_duration_days": 89 }, { "site_id": "S051", "site_name": "Banyan Street Tower", "estimated_materials_cost": 88000, "actual_materials_cost": 92500, "estimated_labor_cost": 62000, "actual_labor_cost": 65500, "estimated_duration_days": 118, "actual_duration_days": 125 }, { "site_id": "S052", "site_name": "Catalpa Grove Center", "estimated_materials_cost": 60000, "actual_materials_cost": 63000, "estimated_labor_cost": 43000, "actual_labor_cost": 45000, "estimated_duration_days": 94, "actual_duration_days": 99 }, { "site_id": "S053", "site_name": "Hawthorn Bay Building", "estimated_materials_cost": 100000, "actual_materials_cost": 105000, "estimated_labor_cost": 71000, "actual_labor_cost": 75500, "estimated_duration_days": 133, "actual_duration_days": 141 }, { "site_id": "S054", "site_name": "Larch Ridge Mall", "estimated_materials_cost": 71000, "actual_materials_cost": 74500, "estimated_labor_cost": 51000, "actual_labor_cost": 53500, "estimated_duration_days": 104, "actual_duration_days": 109 }, { "site_id": "S055", "site_name": "Mimosa Valley Office", "estimated_materials_cost": 47000, "actual_materials_cost": 49500, "estimated_labor_cost": 33000, "actual_labor_cost": 35000, "estimated_duration_days": 83, "actual_duration_days": 87 }, { "site_id": "S056", "site_name": "Rowan Hill Plaza", "estimated_materials_cost": 84000, "actual_materials_cost": 88000, "estimated_labor_cost": 59000, "actual_labor_cost": 62500, "estimated_duration_days": 115, "actual_duration_days": 121 }, { "site_id": "S057", "site_name": "Tupelo Point Complex", "estimated_materials_cost": 58000, "actual_materials_cost": 61000, "estimated_labor_cost": 41000, "actual_labor_cost": 43500, "estimated_duration_days": 92, "actual_duration_days": 97 }, { "site_id": "S058", "site_name": "Buckeye Creek Tower", "estimated_materials_cost": 95000, "actual_materials_cost": 99500, "estimated_labor_cost": 67000, "actual_labor_cost": 71000, "estimated_duration_days": 126, "actual_duration_days": 133 }, { "site_id": "S059", "site_name": "Ginkgo Street Center", "estimated_materials_cost": 72000, "actual_materials_cost": 75500, "estimated_labor_cost": 51000, "actual_labor_cost": 53500, "estimated_duration_days": 103, "actual_duration_days": 108 }, { "site_id": "S060", "site_name": "Linden Bay Building", "estimated_materials_cost": 55000, "actual_materials_cost": 57500, "estimated_labor_cost": 39000, "actual_labor_cost": 41000, "estimated_duration_days": 89, "actual_duration_days": 93 }, { "site_id": "S061", "site_name": "Acacia Ridge Mall", "estimated_materials_cost": 86000, "actual_materials_cost": 90500, "estimated_labor_cost": 61000, "actual_labor_cost": 64500, "estimated_duration_days": 117, "actual_duration_days": 124 }, { "site_id": "S062", "site_name": "Jacaranda Valley Office", "estimated_materials_cost": 64000, "actual_materials_cost": 67000, "estimated_labor_cost": 45000, "actual_labor_cost": 47500, "estimated_duration_days": 98, "actual_duration_days": 103 }, { "site_id": "S063", "site_name": "Mahogany Grove Plaza", "estimated_materials_cost": 97000, "actual_materials_cost": 101500, "estimated_labor_cost": 69000, "actual_labor_cost": 72500, "estimated_duration_days": 128, "actual_duration_days": 135 }, { "site_id": "S064", "site_name": "Teak Hill Complex", "estimated_materials_cost": 68000, "actual_materials_cost": 71500, "estimated_labor_cost": 48000, "actual_labor_cost": 50500, "estimated_duration_days": 100, "actual_duration_days": 105 }, { "site_id": "S065", "site_name": "Bamboo Point Tower", "estimated_materials_cost": 79000, "actual_materials_cost": 83000, "estimated_labor_cost": 56000, "actual_labor_cost": 59000, "estimated_duration_days": 111, "actual_duration_days": 117 }, { "site_id": "S066", "site_name": "Ebony Creek Center", "estimated_materials_cost": 53000, "actual_materials_cost": 55500, "estimated_labor_cost": 37000, "actual_labor_cost": 39000, "estimated_duration_days": 87, "actual_duration_days": 91 }, { "site_id": "S067", "site_name": "Sandalwood Street Building", "estimated_materials_cost": 91000, "actual_materials_cost": 95500, "estimated_labor_cost": 64000, "actual_labor_cost": 67500, "estimated_duration_days": 120, "actual_duration_days": 127 }, { "site_id": "S068", "site_name": "Rosewood Bay Mall", "estimated_materials_cost": 61000, "actual_materials_cost": 64000, "estimated_labor_cost": 43000, "actual_labor_cost": 45500, "estimated_duration_days": 94, "actual_duration_days": 99 }, { "site_id": "S069", "site_name": "Teak Valley Office", "estimated_materials_cost": 75000, "actual_materials_cost": 78500, "estimated_labor_cost": 54000, "actual_labor_cost": 56500, "estimated_duration_days": 107, "actual_duration_days": 113 }, { "site_id": "S070", "site_name": "Zebrawood Ridge Plaza", "estimated_materials_cost": 50000, "actual_materials_cost": 52500, "estimated_labor_cost": 35000, "actual_labor_cost": 37000, "estimated_duration_days": 84, "actual_duration_days": 88 }, { "site_id": "S071", "site_name": "Boxwood Hill Tower", "estimated_materials_cost": 87000, "actual_materials_cost": 91000, "estimated_labor_cost": 61000, "actual_labor_cost": 64500, "estimated_duration_days": 116, "actual_duration_days": 123 }, { "site_id": "S072", "site_name": "Lignum Point Complex", "estimated_materials_cost": 63000, "actual_materials_cost": 66000, "estimated_labor_cost": 44000, "actual_labor_cost": 46500, "estimated_duration_days": 97, "actual_duration_days": 102 }, { "site_id": "S073", "site_name": "Butternut Creek Center", "estimated_materials_cost": 99000, "actual_materials_cost": 103500, "estimated_labor_cost": 70000, "actual_labor_cost": 74000, "estimated_duration_days": 130, "actual_duration_days": 138 }, { "site_id": "S074", "site_name": "Myrtle Street Building", "estimated_materials_cost": 70000, "actual_materials_cost": 73500, "estimated_labor_cost": 50000, "actual_labor_cost": 52500, "estimated_duration_days": 102, "actual_duration_days": 107 }, { "site_id": "S075", "site_name": "Olive Bay Mall", "estimated_materials_cost": 46000, "actual_materials_cost": 48500, "estimated_labor_cost": 32000, "actual_labor_cost": 34000, "estimated_duration_days": 82, "actual_duration_days": 86 }, { "site_id": "S076", "site_name": "Sapele Ridge Office", "estimated_materials_cost": 83000, "actual_materials_cost": 87000, "estimated_labor_cost": 58000, "actual_labor_cost": 61500, "estimated_duration_days": 114, "actual_duration_days": 120 }, { "site_id": "S077", "site_name": "Wenge Valley Plaza", "estimated_materials_cost": 57000, "actual_materials_cost": 60000, "estimated_labor_cost": 40000, "actual_labor_cost": 42500, "estimated_duration_days": 91, "actual_duration_days": 96 }, { "site_id": "S078", "site_name": "Bubinga Grove Tower", "estimated_materials_cost": 94000, "actual_materials_cost": 98500, "estimated_labor_cost": 66000, "actual_labor_cost": 70000, "estimated_duration_days": 125, "actual_duration_days": 132 }, { "site_id": "S079", "site_name": "Kingwood Hill Complex", "estimated_materials_cost": 71000, "actual_materials_cost": 74500, "estimated_labor_cost": 51000, "actual_labor_cost": 53500, "estimated_duration_days": 103, "actual_duration_days": 108 }, { "site_id": "S080", "site_name": "Tamo Point Center", "estimated_materials_cost": 54000, "actual_materials_cost": 56500, "estimated_labor_cost": 38000, "actual_labor_cost": 40000, "estimated_duration_days": 88, "actual_duration_days": 92 }, { "site_id": "S081", "site_name": "Afrormosia Creek Building", "estimated_materials_cost": 85000, "actual_materials_cost": 89500, "estimated_labor_cost": 60000, "actual_labor_cost": 63500, "estimated_duration_days": 115, "actual_duration_days": 122 }, { "site_id": "S082", "site_name": "Etimoe Street Mall", "estimated_materials_cost": 62000, "actual_materials_cost": 65000, "estimated_labor_cost": 44000, "actual_labor_cost": 46000, "estimated_duration_days": 96, "actual_duration_days": 101 }, { "site_id": "S083", "site_name": "Padauk Bay Office", "estimated_materials_cost": 96000, "actual_materials_cost": 100500, "estimated_labor_cost": 68000, "actual_labor_cost": 72000, "estimated_duration_days": 127, "actual_duration_days": 134 }, { "site_id": "S084", "site_name": "Cumaru Ridge Plaza", "estimated_materials_cost": 69000, "actual_materials_cost": 72500, "estimated_labor_cost": 49000, "actual_labor_cost": 51500, "estimated_duration_days": 101, "actual_duration_days": 106 }, { "site_id": "S085", "site_name": "Ipe Valley Tower", "estimated_materials_cost": 78000, "actual_materials_cost": 82000, "estimated_labor_cost": 56000, "actual_labor_cost": 58500, "estimated_duration_days": 110, "actual_duration_days": 116 }, { "site_id": "S086", "site_name": "Jatoba Hill Complex", "estimated_materials_cost": 52000, "actual_materials_cost": 54500, "estimated_labor_cost": 36000, "actual_labor_cost": 38500, "estimated_duration_days": 86, "actual_duration_days": 90 }, { "site_id": "S087", "site_name": "Tigerwood Point Center", "estimated_materials_cost": 90000, "actual_materials_cost": 94000, "estimated_labor_cost": 63000, "actual_labor_cost": 66500, "estimated_duration_days": 119, "actual_duration_days": 126 }, { "site_id": "S088", "site_name": "Santos Creek Building", "estimated_materials_cost": 60000, "actual_materials_cost": 63000, "estimated_labor_cost": 42000, "actual_labor_cost": 44500, "estimated_duration_days": 93, "actual_duration_days": 98 }, { "site_id": "S089", "site_name": "Amendoim Street Mall", "estimated_materials_cost": 74000, "actual_materials_cost": 77500, "estimated_labor_cost": 53000, "actual_labor_cost": 55500, "estimated_duration_days": 106, "actual_duration_days": 112 }, { "site_id": "S090", "site_name": "Garapa Bay Office", "estimated_materials_cost": 49000, "actual_materials_cost": 51500, "estimated_labor_cost": 34000, "actual_labor_cost": 36500, "estimated_duration_days": 83, "actual_duration_days": 87 }, { "site_id": "S091", "site_name": "Massaranduba Ridge Plaza", "estimated_materials_cost": 86000, "actual_materials_cost": 90000, "estimated_labor_cost": 60000, "actual_labor_cost": 63500, "estimated_duration_days": 116, "actual_duration_days": 123 }, { "site_id": "S092", "site_name": "Peroba Valley Tower", "estimated_materials_cost": 64000, "actual_materials_cost": 67000, "estimated_labor_cost": 45000, "actual_labor_cost": 47500, "estimated_duration_days": 98, "actual_duration_days": 103 }, { "site_id": "S093", "site_name": "Tatajuba Grove Complex", "estimated_materials_cost": 98000, "actual_materials_cost": 102500, "estimated_labor_cost": 69000, "actual_labor_cost": 73000, "estimated_duration_days": 129, "actual_duration_days": 137 }, { "site_id": "S094", "site_name": "Angico Hill Center", "estimated_materials_cost": 68000, "actual_materials_cost": 71500, "estimated_labor_cost": 48000, "actual_labor_cost": 50500, "estimated_duration_days": 100, "actual_duration_days": 105 }, { "site_id": "S095", "site_name": "Roxinho Point Building", "estimated_materials_cost": 77000, "actual_materials_cost": 81000, "estimated_labor_cost": 55000, "actual_labor_cost": 57500, "estimated_duration_days": 109, "actual_duration_days": 115 }, { "site_id": "S096", "site_name": "Angelim Creek Mall", "estimated_materials_cost": 51000, "actual_materials_cost": 53500, "estimated_labor_cost": 36000, "actual_labor_cost": 38000, "estimated_duration_days": 85, "actual_duration_days": 89 }, { "site_id": "S097", "site_name": "Goncalo Street Tower", "estimated_materials_cost": 88000, "actual_materials_cost": 92000, "estimated_labor_cost": 62000, "actual_labor_cost": 65000, "estimated_duration_days": 118, "actual_duration_days": 125 }, { "site_id": "S098", "site_name": "Cupiuba Bay Office", "estimated_materials_cost": 59000, "actual_materials_cost": 62000, "estimated_labor_cost": 42000, "actual_labor_cost": 44000, "estimated_duration_days": 92, "actual_duration_days": 97 }, { "site_id": "S099", "site_name": "Jequitiba Ridge Plaza", "estimated_materials_cost": 93000, "actual_materials_cost": 97500, "estimated_labor_cost": 66000, "actual_labor_cost": 69500, "estimated_duration_days": 123, "actual_duration_days": 130 }, { "site_id": "S100", "site_name": "Sucupira Valley Complex", "estimated_materials_cost": 67000, "actual_materials_cost": 70500, "estimated_labor_cost": 47000, "actual_labor_cost": 49500, "estimated_duration_days": 99, "actual_duration_days": 104 }, { "site_id": "S101", "site_name": "Canela Hill Tower", "estimated_materials_cost": 82000, "actual_materials_cost": 86000, "estimated_labor_cost": 58000, "actual_labor_cost": 61000, "estimated_duration_days": 113, "actual_duration_days": 119 }, { "site_id": "S102", "site_name": "Freijo Point Center", "estimated_materials_cost": 56000, "actual_materials_cost": 58500, "estimated_labor_cost": 39000, "actual_labor_cost": 41500, "estimated_duration_days": 90, "actual_duration_days": 94 }, { "site_id": "S103", "site_name": "Muiracatiara Creek Building", "estimated_materials_cost": 89000, "actual_materials_cost": 93500, "estimated_labor_cost": 63000, "actual_labor_cost": 66500, "estimated_duration_days": 119, "actual_duration_days": 126 }, { "site_id": "S104", "site_name": "Cacheta Street Mall", "estimated_materials_cost": 63000, "actual_materials_cost": 66000, "estimated_labor_cost": 44000, "actual_labor_cost": 46500, "estimated_duration_days": 97, "actual_duration_days": 102 }, { "site_id": "S105", "site_name": "Louro Bay Office", "estimated_materials_cost": 95000, "actual_materials_cost": 99000, "estimated_labor_cost": 67000, "actual_labor_cost": 71000, "estimated_duration_days": 126, "actual_duration_days": 133 } ]