--- name: progressive-estimation description: "Estimate AI-assisted and hybrid human+agent development work with explicit PERT assumptions and calibration feedback loops" category: project-management risk: safe source: community date_added: "2026-03-10" author: Enreign tags: - estimation - project-management - pert - sprint-planning - ai-agents tools: - claude --- # Progressive Estimation Estimate AI-assisted and hybrid human+agent development work using three-point estimates, stated uncertainty assumptions and calibration feedback loops. ## Overview Progressive Estimation adapts to your team's working mode — human-only, hybrid, or agent-first — choosing explicit assumptions for each. Estimates remain uncertain and require local calibration. ## When to Use This Skill - Estimating development tasks where AI agents handle part of the work - Sprint planning with hybrid human+agent teams - Batch sizing a backlog (handles 5 or 500 issues) - Staffing and capacity planning with agent multipliers - Release date forecasting with confidence intervals ## How It Works 1. **Mode Detection** — Determines if the team works human-only, hybrid, or agent-first 2. **Task Classification** — Categorizes by size (XS–XL), complexity, and risk 3. **Formula Application** — Applies locally measured multipliers when available, or clearly labeled scenarios 4. **PERT Calculation** — Produces expected values using three-point estimation 5. **Confidence Bands** — Generates percentiles only with a specified, calibrated forecast model 6. **Output Formatting** — Formats for Linear, JIRA, ClickUp, GitHub Issues, Monday, or GitLab 7. **Calibration** — Feeds back actuals to improve future estimates ## Examples **Single task:** > "Estimate building a REST API with authentication using Claude Code" **Batch mode:** > "Estimate these 12 JIRA tickets for our next sprint" **With context:** > "We have 3 developers using AI agents for ~60% of implementation. Estimate this feature." ## Estimation procedure Record scope, dependencies, acceptance criteria and whether durations mean effort or elapsed time. Elicit optimistic O, most likely M and pessimistic P in the same units, with O ≤ M ≤ P. A conventional PERT approximation is E = (O + 4M + P)/6 and SD ≈ (P − O)/6; these are modeling assumptions, not observed certainty. For O=2, M=4, P=12 hours, E=5 hours and SD≈1.67 hours. Record the assumptions behind each bound. Do not derive P50/P75/P90 directly from the mean or label a range a confidence interval without a stated distribution and method. For a project forecast include dependencies, correlated risks, review/queue time and limited human capacity. Use actual comparable completed tasks to calibrate AI multipliers; absent data, present explicit scenarios rather than claiming a research-backed speedup. Report actuals against the original scope and revise future forecasts. This guide does not bundle an estimation engine or calibration database. ## Best Practices - Start with a single task to calibrate before moving to batch mode - Feed back actual completion times to improve the calibration system - Use "instant mode" for quick T-shirt sizing without full PERT analysis - Be explicit about team composition and agent usage percentage ## Common Pitfalls - **Problem:** Overconfident estimates **Solution:** Use P75 or P90 for commitments, not P50 - **Problem:** Missing context **Solution:** The skill asks clarifying questions — provide team size and agent usage - **Problem:** Stale calibration **Solution:** Re-calibrate when team composition or tooling changes significantly ## Related Skills - `@sprint-planning` - Sprint planning and backlog management - `@project-management` - General project management workflows - `@capacity-planning` - Team velocity and capacity planning ## Additional Resources - [Source Repository](https://github.com/Enreign/progressive-estimation) - [Installation Guide](https://github.com/Enreign/progressive-estimation/blob/main/INSTALLATION.md) - [Research References](https://github.com/Enreign/progressive-estimation/tree/main/references) ## Limitations - Use this skill only when the task clearly matches the scope described above. - Do not treat the output as a substitute for environment-specific validation, testing, or expert review. - Stop and ask for clarification if required inputs, permissions, safety boundaries, or success criteria are missing.