Task,Duration,Start,Resource,Dependency Task 1,5,12/31/2016,Joe, Task 2,10,12/31/2016,Mark,Task 1 Task 3,1,12/31/2016,Kevin,Task 1 Task 4,3,12/31/2016,Leslie,Task 2 Task 5,15,12/31/2016,Joe, Task 6,3,12/31/2016,Roger, Task 7,10,12/31/2016,Joe,Task 5 Task 8,1,12/31/2016,Joe, Task 9,3,12/31/2016,Leslie,Task 8 Task 10,3,12/31/2016,Kevin,Task 9 Task 11,2,12/31/2016,Joe,Task 10 Task 12,5,12/31/2016,Leslie,Task 11 Task 13,1,12/31/2016,Joe, Task 14,3,12/31/2016,Mark,Task 2 Task 15,5,12/31/2016,Joe/Roger,Task 4 Task 16,1,12/31/2016,Joe, Task 17,3,12/31/2016,Joe,Task 16 Task 18,3,12/31/2016,Andy/April,Task 17 Task 19,1,12/31/2016,Joe, Task 20,1,12/31/2016,Joe, Task 21,1,12/31/2016,Kevin, Task 22,3,12/31/2016,Joe,Task 21 Task 23,3,12/31/2016,Mark,Task 22 Task 24,3,12/31/2016,Leslie,Task 23 Task 25,2,12/31/2016,Joe, Task 26,2,12/31/2016,Andy, Task 27,2,12/31/2016,April, Task 28,1,12/31/2016,Joe, Task 29,5,12/31/2016,Mark, Task 30,1,12/31/2016,Joe,Task 27